Insight
One atomic statement made by an expert, a student or a publication, with its evidence status.
Expert Open for expert review · What do these labels mean?
On a Swedish project, a maximum embodied carbon value per square metre was written into the tender documents to the general contractor; over roughly 12 months of construction the team drove the result down to 159 kg/m², and the whole effort cost just under 1% of total investment. A recent Czech project (Ostrava) reached under 293 kg/m² — but without the tender requirement.
— Paraphrased from the lecture
| Where in the source | ~00:24 — anchor: “part of the tender documentation” |
| Confidence | check — the Czech project’s place name reads “Ostroff” in the transcript |
Context
Fojtík (Panattoni) compares embodied carbon results from Panattoni projects in different markets. In Sweden, a maximum embodied carbon value was part of the tender to the general contractor; a recent Czech project did well without such a requirement. The Czech project’s location is garbled in the transcript (“Ostroff”, in the north of the country).
From the transcript
[…] you see the project which is currently finished in Sweden. There is also embodied carbon part of the tender documentation. So if you are dealing with a general contractor, you put there some maximum value of the embodied carbon per square metre. But our colleague in the Sweden was able to reduce during the, let’s say, 12 months of the construction to final result 159 kilogram per square meter, which is excellent. And all of it, it was just under 1% of the total cost of the investment. […] one of our latest project is in the [Ostroff], north of the Czech Republic, and we get under 293 kilogram per square meter, which is also some very good number […] But it wasn’t part of the tender documentation […]
Automatic transcript, presentation, 00:24:26. Lightly cleaned: repeated words and fillers removed, omissions marked […], editorial insertions in [brackets].
Connections
- Source: From Model to Reality – Sustainability in Industrial Buildings
- Challenges: Embodied carbon of new and demolished warehouses
- Metrics: Embodied carbon intensity
Something wrong or missing? Suggest a correction