All insights with who made them and where their evidence stands. Rebuilt automatically from the properties of all notes — edit the notes, not this page.

700 insights — atomic statements by experts, students and publications. Each carries who made it and where its evidence stands; see Evidence status.

InsightStatementLabelsSourceAbout
+10% net gain set at concept stageOn Bestseller the team set an early-stage target of at least +10% biodiversity net gain, which then steered the strategy and concept phases.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureHabitat loss and cut ecological corridors, Biodiversity net gain
~20% cost premium, disclosed up front, not negotiated laterWith prices fluctuating after the start of the war in Ukraine, biogenic construction looked ~20% more expensive. Because the ambition was fixed at the outset and the premium flagged early, the project avoided line-by-line bargaining.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusEmbodied carbon of new and demolished warehouses, Construction cost
0.5 kN per m² off the brief, and everything gets cheaperOn a London flagship tower, the design floor load would normally have been 3 kN/m²; they convinced the client to accept 2.5, which cascaded through the whole structure as cost and carbon savings.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses, Structural utilisation, Construction cost
1,500 assets screened in a week — on five data fieldsEY’s in-house climate risk tool covers up to 2,000 companies/assets, with ~1,500 the largest job actually run, deliverable “within the week” given good data. The required data is minimal: building type, construction material, location, size, and a few more.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
1,500 lux is where people improvise blindsHer own floor-measured metric uses a 1,500 lux maximum, a threshold derived not from theory but from studies observing the point at which office workers spontaneously start rigging up improvised shading.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLDeep, dark and noisy workplaces, Daylight autonomy
1,500 people have touched data centres in one consultancyRamboll has roughly 1,500 staff with partial or full data centre experience; a concept design may take a handful of people, while detailed design scales rapidly across MEP, structures and architecture.Expert Open for expert reviewCloud in the city – data centres, urban development and implications—
1,900 heat inspections, zero citationsAround 1.8 million people work in US warehouses with heat-stress exposure, a workforce that nearly doubled between 2017 and 2022, in 20 billion sq ft of space with 30–40 ft ceilings. OSHA has run over 1,900 heat-related inspections since April 2022 — nearly tenfold the 2021 rate — and issued seven hazard alert letters to warehousing companies, with no citations or fines. Federal guidance puts heat-illness risk from strenuous work at 77 °F WBGT; workers at one air hub logged indoor temperatures up to 89 °F.External Open for expert reviewNBC News investigation, 2023Deep, dark and noisy workplaces, Thermal comfort
10,000 m² of green roof, 300 trees, a cyclists’ rampRoughly 10,000 m² of green roofs storing rainfall in soil rather than shedding it, more than 300 trees, and a separate access ramp built specifically so cyclists do not share the car route; the metro entrance and a small square were upgraded jointly with the City of Prague.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLStormwater and sealed surfaces on logistics sites, Green roof coverage, Tree count and canopy cover
10% GWP cut from six combined measuresCampus Science Park in Brno, the first LEED v4 certified building in the country, achieved a 10% reduction in global warming potential — plus photochemical oxidants, acidification and non-renewable energy — across a complex of six calculated measures.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLEmbodied carbon of new and demolished warehouses, Whole-life carbon
13.5 Gt per yr, and where it actually sitsBuildings put at ~37% of global CO2, equal to about 13.5 Gt/yr; ~10 Gt operational in existing buildings, ~3.5 Gt/yr embodied, the vast majority in concrete, aluminium and steel.Expert DisputedNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses
159 kg per m² for under 1% of investment costOn a Swedish project, a maximum embodied carbon value per square metre was written into the tender documents to the general contractor; over roughly 12 months of construction the team drove the result down to 159 kg/m², and the whole effort cost just under 1% of total investment. A recent Czech project (Ostrava) reached under 293 kg/m² — but without the tender requirement.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
177 boreholes, 150 metres deepHeating and cooling run on ground-source heat pumps served by 177 drilled cores 150 m deep; the system regenerates heat in the soil through the cooling season, and waste heat from cooling is recovered for domestic hot water.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLHigh operational energy demand
20,000 factory visitors a year, aiming at 25,000Czech open-house culture is strong: the existing cake factory receives around 20,000 visitors a year through glass panels and VIP walkthroughs; the new project is expected to triple that, and the brewery client is targeting ~25,000 a year.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Closed sites that give little back to the city, Social interaction index
2027–2030 – whole-life carbon becomes mandatoryUnder the recast EPBD, member states must set GWP limits by 2027; public buildings must prove GWP from January 2028; from January 2030 all new buildings must demonstrate whole-life carbon assessment. Alongside EU taxonomy, described as a large problem for most EU countries.Expert DisputedLogistics Development in the concept of certification and LCAEmbodied carbon of new and demolished warehouses, Whole-life carbon
2050-proof is not enough; make it 2070-proofThe studio used to say all designs should be 2050 proof; it now says 2070, because the project lifespans they work with run 50 years and beyond.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Buildings that change slower than logistics
21% and 25% of the floor unusable — and legalOn a real Prague office floor plate, roughly 21% of the assessed area suffered excessive direct sunlight exposure and 25% excessive illuminance requiring occupants to shade — and that same floor plan would pass the Czech code without objection.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLDeep, dark and noisy workplaces
250 pages of German, six weeks to a masterplanFor the Max Planck Institute competition the team received ~3.5 GB / ~250 pages of technical German documentation with one German speaker on the team and six weeks to produce a concept. All PDFs were loaded into a secured NotebookLM space and queried conversationally, with citations back to source. The design director, who “only understands audio,” was given an AI-generated podcast of the brief for the flight to Munich.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
27 neighbourhoods, 15,000 datasets, 1,200 answersThe study tested loneliness, house prices and visitor numbers across 27 Copenhagen neighbourhoods, combining statistics, web-scraped data, questionnaires, mobile geolocation and credit-card transaction flows.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient NeighborhoodsSocial interaction index
297 hectares of green belt for one rail interchangeThe West Midlands Interchange strategic rail freight interchange was approved in May 2020 over 297 hectares of designated green belt, against the local council’s warning of “significant encroachment into the countryside” and its fear the rail link was a “Trojan Horse” for road-served warehousing. Approval was justified on GBP 680m/year of gross value added.External Open for expert reviewPlanning Resource, 2020Land take of logistics buildings, Land take
35,000 m² of green façade, possibly the world’s largestThe two high bays (roughly 140 x 120 m in plan, 35 m tall) carry close to 35,000 m² of green façade.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusHabitat loss and cut ecological corridors, Green plot ratio
350 people vs 6,000 next doorThe neighbouring bol.com facility is comparable in size (~150,000 m²) but manual: reportedly ~6,000 staff against Bestseller’s ~350 on its largest shift. Much of that workforce would be imported labour, and the operator reportedly sought temporary on-site housing — blocked because residential use is not permitted inside a logistics master plan.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusSpace, energy and labour needs changing with automation, Level of automation, Jobs created
355 GW sits on Europe’s big roofsThe JRC’s building-level model of all 271 million EU buildings puts total rooftop PV potential at ~2.3 TWp / ~2,750 TWh a year — 40% of electricity in a zero-emission 2050. Non-residential roofs alone hold ~500 GWp, and large commercial buildings over 2,000 m² account for about 355 GW: more than half the EU’s entire 700 GW 2030 target, on the roofs of the building type this article is about.External Open for expert reviewJRC - Nature Energy, 2026High operational energy demand, Rooftop PV generation
36,000 lorry trips removed by bargeFranprix has supplied 300 Paris stores by river since 2012, running up to 42–48 containers a day from Bonneuil-sur-Marne to Quai de la Bourdonnais: 36,000 truck trips and 450,000 vehicle-km avoided over ten years, 250 tonnes of CO2 saved a year. Other Seine operators include Fludis (electric barge plus e-bikes) and a cable-car system that removed 10,000 trucks a month from one construction project.External Open for expert reviewAIVP, Paris – transport on the River SeineLast-mile delivery emissions and traffic, Road freight impact
4.7% vs 8–9% vs 14–15%Citing Eurostat, total built-up area at 4.7% of Czech territory against 8–9% in Germany and 14–15% in Benelux, arguing there is headroom before CZ reaches Western levels of land consumption.Expert DisputedIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formLand take of logistics buildings
5% of Prague dug a metre deepTo make material extraction legible: 24 million cubic metres of stone, sand and brick were extracted over five years — equivalent to digging 5% of Prague to a depth of one metre. Prague’s flushing and sink use runs to 12 billion litres a year, roughly a small dam or 5,000 Olympic pools.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELL—
50 hours, 20 hours, 30 minutesLCA from a bill of quantities takes roughly 50 hours and gives the best accuracy; a well-built BIM model (LOD 300 recommended) cuts that to around 20 hours; a simplified tool takes about 30 minutes with accuracy varying by roughly 10–20%. Garbage in a BIM model propagates straight into the result.Expert Open for expert reviewLogistics Development in the concept of certification and LCAEmbodied carbon intensity
50–80,000 people a day use their toiletTheir first Prague project was the toilets of a large shopping centre, used by 50–80,000 visitors per day at peak. Possibly the most-used architecture they will ever make, and entirely unattributed.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
58% of the site lost, biodiversity still up 10–11%Of nearly 300,000 m² of original landscape, only ~42% remains landscape after building, roofs and hardscape — yet the BNG comparison shows a ~10–11% increase, achieved through species variety rather than area.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusHabitat loss and cut ecological corridors, Biodiversity net gain, Land take
6,500 mayors, none of them motivated~6,500 municipalities, most under 1,000 inhabitants, each with its own master plan. Development brings extra work, pressure on schools and local opposition; the central grant arrives regardless.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
7,000 m² of farming on a Paris data centre roofEquinix, a colocation provider, built a data centre in northern Paris with a greenhouse urban farm on top, heated by the building’s waste heat and producing vegetables and fruit — nearly 7,000 square metres of farming.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsWaste heat and cooling of data centres, Waste heat recovery, Katrin Rybinskiy
78 of 87 assets already at high drought riskFrom an anonymised client portfolio: under the shown scenario/horizon (RCP 4.5, 2050), roughly 78 of 87 assets sit at high or very high drought risk today, with no change into the future; for temperature, 43 assets move into very high risk. Some risk is not future — it is already baseline.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
78% of land already alteredHumans have cultivated, exploited, drained or coated 78% of land globally, leaving very little real nature — framed as the root of both the climate and biodiversity crises.Expert DisputedNature positive by design – Creating lasting impact by designing for and with nature—
8–10% of the area, 50% of the peopleOnly ~8–10% of the 155,000 m² is administration area, yet staffing between automated hall and offices is roughly equal.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusSpace, energy and labour needs changing with automation
80–90% of network designs never reach the marketPer his network-design partners, the large majority of commissioned supply-chain optimisation studies die at costing, exactly as architectural concepts do.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
80% of the market need, not 100% of one tenantThe investor horizon is 15–20 years while leases run 5–10; a building must fit roughly 80% of market demand so tenants can be swapped without touching the asset’s fundamentals.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formBuildings that change slower than logistics, Adaptability
80% of what a city needs is made outside itUrbanism’s problem is that most of what a city consumes is produced elsewhere, so out-of-town facilities should combine nature outside with production inside and serve the city directly.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
85 GW blocked by roofs that can’t take the weightA Becquerel Institute analysis finds more than 85 GW of European rooftop potential — 38 GW industrial, 48 GW commercial — is unreachable with conventional modules because the roofs cannot carry over 10 kg/m² without reinforcement. Lightweight modules at least 50% lighter would unlock it.External Open for expert reviewBecquerel Institute, via pv magazine, March 2026High operational energy demand, Structural utilisation, Rooftop PV generation
85% of rating schemes set no biodiversity objectivesMost green building rating schemes do not specify biodiversity objectives (85 %).External Open for expert reviewEvaluating biodiversity criteria in green building rating schemesHabitat loss and cut ecological corridors
90% of Dutch occupiers would pay more for green spaceIn the Netherlands most industrial occupiers accept a rent premium for sustainable space, driven mainly by compliance needs.External Open for expert reviewSustainability Unboxed – Delivering on Logistics and Distribution WarehousesGreen rent premium
A 1 – 18 contrast ratio gives you migrainesWith a monitor fixed at 300 cd/m², immediately adjacent surfaces can exceed 6,000 cd/m², and even distant surfaces such as the facade or window leave a ratio of about 1:18 — high enough to be linked to migraines, poor concentration and lost productivity.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLDeep, dark and noisy workplaces
A 160 bps development spread for big-box logisticsThe development spread for European big-box logistics was about 160 basis points in January 2025.External Open for expert reviewClarion Partners – Capitalising on the New Market Cycle with Modern Logistics (2025)Designing for an unknown tenant
A baseline they never intended to buildCertain from the start they would not build in concrete and steel, the team still calculated the full carbon cost of a conventional structure purely as a scoring baseline — yielding a claimed ~30–37% reduction on structural decisions alone.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
A bird island as design precedentThe site sits on the Flevopolder, entirely reclaimed land with very low biodiversity. Offshore lies a second reclaimed-land project built purely to attract migrating birds — that precedent triggered the idea that a logistics site’s leftover land could be nature rather than mown lawn.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusHabitat loss and cut ecological corridors
A blank page as a portfolio slideTo make the point about anonymous practice, they show an empty slide.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
A brick shortage, not ESG, opened the doorThe pitch that got CLT accepted was a 2021 brick shortage and price spike, not carbon. At the time there was no discussion of carbon footprint at all with the client; the ESG framing arrived only afterwards.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itEmbodied carbon of new and demolished warehouses
A company that owns nothing but its people’s timeIllustrating HR risk: EY globally has over 400,000 colleagues but the firm itself “does not own anything, just owns our time” — so any acquirer’s due diligence would be about whether the staff are happy and staying.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
A dead steel mill is infrastructureA former steel mill already had 30 MW of power, 1,500 truck movements a day and 6,000 workers arriving. The problem is that Czech zoning does not guarantee you inherit it, and the surrounding city consumed the road, sewage and electrical capacity in the intervening decade.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
A dump site that forbade digging became islandsOn an 18-hectare former dump, piling, excavation and parking basements were all impossible; the constraint became the concept — neighbourhoods raised as real islands ~2 m above a central wetland that absorbs stormwater, with parking pushed to garages on a peripheral ring road.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient NeighborhoodsStormwater and sealed surfaces on logistics sites, Stormwater retention volume
A forgotten typology that used to be the highlightMost architects consider warehouses and factories ugly and boring, and the public never wants to visit one — yet in an earlier era the factory was the highlight of architecture and urbanism, an open, inviting area contributing to the city economically and socially.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’—
A further wave of logistics construction is expected in CzechiaA large further wave of logistics construction is expected in Czechia.Expert Open for expert reviewPartner feedback – final review (2026)Land take of logistics buildings
A green roof without maintenance turns grey againRoofing a whole warehouse in green scores well and addresses heat island, but unmaintained green roofs die. The maintenance regime — who will care for it — must be designed alongside it.Expert Open for expert reviewLogistics Development in the concept of certification and LCAHabitat loss and cut ecological corridors, Green roof coverage
A greenwash premium of about 10%There are companies charging roughly 10% more for materials branded “green something or other” that are neither clever nor particularly low carbon.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and Delivery—
A heart that does not stop beatingThe pandemic proved logistics is non-substitutable: retail can move online and offices home for a year, but stopping a fulfilment centre or a pharma flow is immediate systemic disruption.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
A High Line for a whole industrial estateAt Volvo’s Lundby campus — a fenced, active R&D and production site the city has grown around — the solution is a skywalk layer using the hilly topography to give the public and soft mobility access over the site.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient NeighborhoodsClosed sites that give little back to the city, Ilinca Maria Baciu
A logistics hotel with football pitches on topSogaris’ Chapelle International, Paris (A26 architectes, 2018), stacks 41,500 m² of programme on a former rail freight yard: 15,000 m² of ground-floor urban logistics designed with capacity for internalised rail freight, offices above, and a roof carrying sports pitches, an urban farm, a restaurant and a fitness club, with a district heating loop fed by waste heat from a data centre. Eleven tenants, around 350 jobs; MIPIM 2018 award for best industrial and logistics development.External Open for expert reviewSogaris, Chapelle InternationalClosed sites that give little back to the city, Mixed-use ratio
A logistics-specific method would start from territoryAn ideal methodology for logistics would reflect the scale, focus on territorial impact, evaluate impacts across categories, and centre transport — named as the biggest problem of this building type — rather than reusing a generic building framework.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
A low-carbon warehouse can win architecture awardsHis closing line, against the assumption that logistics sheds sit outside architectural ambition.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and Delivery—
A masterplan brief built from scraped InstagramFor an industrial harbour competition in Copenhagen the team scraped social media imagery of the site, classified content with Clarifai (trees, bikes, lanes, buildings) and clustered sentiment and time-of-day to derive planning recommendations. They flag the bias risk explicitly: if the data is generated by whoever happens to be on site, you design for those people.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
A physical sandbox for landscape designThe landscape team uses an augmented-reality sandbox with a depth sensor that registers topography live and links back to the Rhino model for terrain, water runoff and soil-balance calculations. Big developers play with it as readily as visiting children do.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
A portfolio’s climate exposure priced at ~EUR 30 millionThe same anonymised assessment translated physical risk into money: the portfolio is or will be affected to the tune of about 30 million euros in required investment or financial losses.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
A quarter of the office is landscapeRoughly 1/4 of Henning Larsen’s staff are landscape architects, brought in as co-authors from project start; Meisel oversees around 150 landscape designers within Ramboll.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
A quarter of the reference building’s energy costThe ČSOB SHQ energy model comes out at about one quarter of the LEED reference case — measured, as LEED requires, in energy cost rather than in technical consumption units.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLHigh operational energy demand
A rain garden answers four risks at onceA single adaptation measure — creating a rain garden — is credited against heat, geotechnical drought, floods, and human health and well-being simultaneously. The tool’s measure library is recommended as design inspiration.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That LastStormwater and sealed surfaces on logistics sites, Wind, heat and missing shade around large buildings
A reflective roof is a public health measureCool roofs cut maximum indoor temperatures by 1.2–3.3 °C in unconditioned buildings and reduce peak cooling demand by 11–27% in air-conditioned ones. A UK study found city-wide cool roofs could offset 18% of heat-related deaths attributable to the urban heat island.External Open for expert reviewUS EPA, Using Cool Roofs to Reduce Heat IslandsDeep, dark and noisy workplaces, Urban heat island effect, Thermal comfort
A room becomes a bicycle facilityWhere floor area happens to be spare, it is easy to designate it a bicycle facility and collect the credit; where there is no spare space, the same provision is almost impossible to insert.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELL—
A rule you cannot enforce is not a ruleevery rule is great, but what do you do if you can’t actually enforce it and there’s no control aroundExpert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubs—
A supplier who had never built at this scaleThe straw supplier had never delivered a project of this size, so the team carried a palette of Plan-B specifications for every ambitious choice — fallbacks pre-agreed to survive fire, humidity or cost objections without changing the design fundamentally.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics Campus—
A swimming pool heated by servers in MilanRamboll is working on a project in Milan pairing a small data centre with a swimming pool heated by its waste heat — his illustration that the type can be small and connected rather than a fortress.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsWaste heat and cooling of data centres, Julia Godard Lombard
A system with a data centre at its heart, not a standalone assetHis key message: treat the facility as a node in an energy, utility and urban system — how power is produced and distributed, how heat and waste are used, how it sits in city and landscape.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsWaste heat and cooling of data centres
A taller shed stores half as much againPer the Ilora glossary, an 11 m (36 ft) clear height stores about 50% more pallets than 7.3 m (24 ft) on the same footprint.External Open for expert reviewIlora.ai – Industrial Real Estate Analytics (glossary)Clear height, Space utilisation
A three-dimensional street inside the shedRather than splitting the building into blue- and white-collar halves, all shared functions sit in a “three-dimensional street” in the overlap zone, so all staff across three shifts pass each other. Explicitly likened to a city street.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusDeep, dark and noisy workplaces
A translucent factory is a light-pollution machineIf you run a 24/7 factory behind a translucent envelope, the building glows: light pollution becomes a design problem. One answer is not lighting it at night — the robots may not mind, and the night shift becomes robotic while people work days.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Visual impact of logistics on neighbours
A two-to-three-tier building taxonomyFulfilment centres of ~100,000 m² (1,000,000 sq ft), potentially two or three levels internally; possibly a regional centre; then a local depot of ~5,000 m² or less on a city’s edge or inside it — expensive land, cheap building, minimal fit-out, “in and out pretty much,” not really storage.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
A vehicle maker rebrands as a mobility providerVolvo positions itself not as a vehicle manufacturer but as a mobility provider with an obligation to sustainable development in the cities where it operates — including a heritage plaza around the building where the first Volvo was made over 100 years ago.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
A view raises memory by 10–25%From a 2013 World Green Building Council survey: a good outside view (park, greenery, river) raised mental function and memory by 10 to 25%, and calls were handled faster.Expert DisputedCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLDeep, dark and noisy workplaces, Worker well-being
A warehouse heating a hospitalA Panattoni warehouse in Rotterdam carries far more PV than it needs and shares energy with local hospitals, with wind generation immediately behind the site. Energy sharing between buildings in a city is already legal and technically possible under Czech energy law.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsHigh operational energy demand, Rooftop PV generation
A warehouse job needs six times the floor of an office jobThe UK’s standard employment density benchmarks give warehousing and distribution 70 m² GEA per full-time employee, rising to 80 m² for large-scale high-bay, against 36 m² for general industrial and 12 m² NIA for a general office.External Open for expert reviewHomes and Communities Agency, Employment Densities Guide, 2nd ed., 2010Jobs created
A warehouse run by four peopleA jd.com warehouse in China is reportedly staffed by four people, while an Ocado facility in the UK runs over 1,000 picking-and-sorting robots.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performanceSpace, energy and labour needs changing with automation, Level of automation
A water treatment plant that is also a walkA Danish water treatment plant is sunk and covered so the interior stays purely technical while the roof reads as continuous surrounding nature that people walk across.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureClosed sites that give little back to the city
A-class stock in CEE went from nothing to best-in-Europe in 30 years30 years ago there was no such thing as an A class modern industrial building in Central and Eastern Europe. It didn’t exist.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
Absorbed airfields are a project typeDownsview Toronto — an old airfield becoming a district for 25,000 people, the biggest urban development in North America — is one instance of a recurring global type: Tegel, Bromma and others, where the city grew around and swallowed the airfield.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
Accelerants trade speed for strengthExtra accelerant can be dosed by a second screw in the nozzle to set material in 20–30 seconds, and you can add as much as you like — but layers that solidify immediately do not bond to the next layer, and the accelerant dose reduces final strength, so an ultra-high-performance mix can end up weaker than ordinary concrete.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Access regulation is the strongest design leverUrban vehicle access regulations — restricting which vehicle classes may enter which parts of the city and when — are quite strong policies shaping which last-mile vehicles are used, effectively forcing smaller electric vehicles and time-windowed delivery.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubsLast-mile delivery emissions and traffic
Adaptability saves carbon but can’t be countedAdaptability and disassembly extend service life and avoid demolition, which is where the big savings are — yet the standards currently do not permit modelling that benefit, partly because a claimed 100-year lifespan is easy greenwashing. The real driver is not material durability but moral service life.Expert Open for expert reviewLogistics Development in the concept of certification and LCABuildings that change slower than logistics, Embodied carbon of new and demolished warehouses, Adaptability
Adaptation is a design-phase decision, not a facilities oneThe assessment chain is exposure → probability of financial loss or extra investment → adaptation plan. The same adaptation measures can simply be taken into account inside the design phase for a new building instead of being bolted on later.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Adaptation measures come with real cost rangesThe most useful output is a PDF summary pairing each risk with each adaptation measure, a range of investment needed, and sometimes a real-life built example with its associated cost — and because the tool is recent, those costs are close to what can actually be expected.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Adaptive reuse gives a sense of place new construction cannotOffered as a design principle from the brewery: the preserved malt house is what anchors the public experience.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Embodied carbon of new and demolished warehouses, Closed sites that give little back to the city
Adiabatic humidification – cheap, hungry for space, no sterilisationSpray humidification is far less energy-intensive than steam and cools the air as it works, but needs substantial plant space and cannot sterilise; steam is energy-hungry yet kills almost all bacteria in the air.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLHigh operational energy demand
Adidas return rates close to 100%Reported second-hand: at some Adidas logistics centres the return rate approaches 100%, driven by consumers ordering three sizes intending to keep one.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics Campus—
Aesthetics is the missing agenda itemThe industry does not discuss beauty, and integrating architecture, biodiversity and appearance is what makes this building type acceptable in an urban fabric.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsVisual impact of logistics on neighbours
After BIM handover, nobody cares about the modelOnce the ribbon is cut the design and BIM models are abandoned; the studio’s next AI frontier is the production phase, where the accumulated model data is currently wasted.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Against the exportable prototypeThe industrial logic of inventing a product and scaling it globally is itself unsustainable: biogenic material should be harvested near where it is used. A prototype should carry a shared core plus components appropriated to local supply chains and end-of-life.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusEmbodied carbon of new and demolished warehouses
AI adoption tripled in two yearsEuropean businesses using at least one AI technology rose from 8% in 2023 to roughly 20% in 2025, with a sharp North–South divide: about 42% of Danish businesses versus around 8% in Poland.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
AI can’t help you innovate on strawPrompting for a Henning Larsen building in straw and biogenic materials returned something close to their own existing Bestseller project — the model is biased toward existing data, which makes it structurally poor at innovation.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
AI governance as culture, not policyUnderstand the bias, communicate openly (18 months ago staff turned their screens away when using Midjourney, treating it as cheating), let adoption be bottom-up, and accept full authorship — the Deloitte Australia lawsuit over bad citations was brought against Deloitte, not the tool.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Always ask which scenario the tool assumesA resilience tool built on an optimistic scenario will report that your building has few risks — and the optimistic scenarios are already being missed “by far.”Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Amazon 2014 vs 2022 – same floorplate, different buildingComparing Dobrovíz (2014) with Kojetín (2022) at similar floor area, 2024 operating data show the newer building far lower in energy use — attributed to envelope quality, heat pumps plus PV, ventilation efficiency, building shape, and a shift to largely robotic operation.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsHigh operational energy demand, Energy use intensity
Amazon locates by unemployment rateAmazon’s buildings in the north of England sit there because the labour is there: a facility needing 3,000 people cannot be staffed in London.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performanceJobs created
Amazon multi-storey – 60–70% self-suppliedThe four-storey ~200,000 m² Amazon facility on a brownfield carries photovoltaics covering an estimated 60–70% of consumption and is described as fossil-free — the project that shifted the market’s sense of what industrial can be.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formHigh operational energy demand, Land take of logistics buildings, On-site renewable energy share
Ambition upgraded mid-project from do-no-harm to net-gainThe biodiversity target began as “don’t affect biodiversity negatively” and was reformulated during the project, as the landscape strategies developed, into increasing site biodiversity.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusHabitat loss and cut ecological corridors, Biodiversity net gain
An honest I don’t know on bioremediationAsked about planting species to absorb truck oils on logistics sites, he declines to answer and redirects to Ramboll’s landscape architects and to Henning Larsen.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and Delivery—
Architect as decision problem solver, not form makerAgainst the image of the architect in a black t-shirt as form maker, they redefine the role for industrial work as a “decision problem solver” — doing calculations, studies and case studies specifically to reveal what the client actually needs.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
Architect wrote the client’s sustainability briefThe competition brief demanded high sustainability ambition without defining it. Henning Larsen researched Bestseller’s own “Fashion Forward” strategy — written for fashion production, not buildings — and translated it into three building-scale ambitions that then governed every design decision.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics Campus—
Architects design assets; money lives at portfolio levelThe stated point of a Big4 team addressing architecture students is to force a zoom-out: connect the asset the designer is drawing to the corporate level, and connect both to risk management.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Architecture as a human resource toolA high-end office built inside an existing logistics warehouse, pitched to the client not as refurbishment but as a recruitment and retention instrument: salary alone no longer attracts talent to an out-of-town shed.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itDeep, dark and noisy workplaces, Worker well-being
Ask whether the warehouse works in a blackoutResilience for logistics means asking operational questions certification does not: can trucks still reach the site in a flood, can the hall keep running through a blackout, what happens to a warehouse full of food.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
Assessment is not optional at this scaleBREEAM and LEED criteria are designed in from the start via a separate specialist body; EIA covers much of the same ground; and because the money is usually a bank loan, the criteria are a financing condition. “In this size, the assessments are really necessary. It cannot happen without those.”Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’—
Australia ships its iron ore around the world and buys it back as steelAustralia extracts iron ore in Western Australia, ships it to China, Japan or Korea for steelmaking, and ships the steel back — “insane” but rational, because no carbon price is embedded in the transaction.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
Automated trucks will not change the loading dockProvided automated trucks keep the same dimensions, loading bays stay as they are — and the expectation is more bays, for more vehicle types. If the vehicle changes shape, the bay becomes a design question again.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Space, energy and labour needs changing with automation, Number of docks, Hynek Hrabík
Automation is a wage-driven substitution, not a technology storyRobotics, AS/RS and AGV picking are spreading specifically because labour costs are rising; if labour is 20–30% of supply-chain cost and automation removes most of it, the payback is large. The building consequence is height, and therefore a permitting fight.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentSpace, energy and labour needs changing with automation, Level of automation
Basements are bad news, full stopPutting anything in the ground is extremely carbon intensive. Even a multi-storey car park above ground beats parking below it. For an underground data centre proposed on biodiversity grounds, he says it wouldn’t help biodiversity either — though an existing hole in the ground changes the maths.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
Bats reframed as a lighting problemOn the Sugar Valley (former Siemens factory, Munich) master plan, protected endangered bats drove dedicated high-level bat homes and, crucially, the outdoor lighting scheme — the office’s lighting specialist calls himself an expert in “light and shadow design” so insects survive and bats aren’t killed at the lamps.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureHabitat loss and cut ecological corridors
Better logistics design eases negotiations with the cityBetter logistics design can make negotiations with the city and authorities easier.Expert Open for expert reviewPartner feedback – final review (2026)Closed sites that give little back to the city, Visual impact of logistics on neighbours
Better toilets make politer shop assistantsThe way into the Penny relationship was staff facilities, not the shop floor. The argument sold to the client was a chain of consequences: better back-of-house space produces less irritable shop assistants, which improves the customer experience.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itDeep, dark and noisy workplaces
Beyond Czech water standards, into BREEAM’sRainfall and infiltration for the whole site are calculated not only to Czech norms but to the stricter standards embedded in BREEAM certification, with additional modelling of alternative scenarios.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsStormwater and sealed surfaces on logistics sites
Big garages flatter your per-m² carbonIn the Skanska Dřevák study, the conventional buildings scored 22–23 kg CO2/m²/yr while their garages scored only 9; because the garages were large, the blended figure fell to 19. The timber building’s higher headline number was only higher against that diluted total.Expert Open for expert reviewLogistics Development in the concept of certification and LCAEmbodied carbon intensity
Big systems mean big impactHer closing argument for why designers should chase industrial and logistics commissions.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Bigger objects print more easily than small onesCounterintuitively, the worst thing to print is a small column: each layer takes so little time that material stacks up before it can gain strength. Prvok used a nozzle roughly 4 cm in diameter with a layer height of about 12 mm; reducing layer height to chase resolution can add around three extra hours of printing.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Biggest cities are not the fastestLondon, Paris and Madrid dominate on GDP scale but the fastest-growing European city economies sit in Central and Eastern Europe (Warsaw cited), because mature economies have less room to expand.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
BIM vs bill-of-quantities differed by only 5%The same Skanska project was calculated both ways; the total GWP differed by only 5%, while the speed ratio was described as 3:2:1.Expert DisputedLogistics Development in the concept of certification and LCAEmbodied carbon intensity
Biodiversity forbidden by food-hygiene lawOn a food production site, strict limits on insects and rodents mean the client asks you not to introduce anything that improves biodiversity — because attracting life outside means poisoning everything outside to keep it out of the factory. International hygiene standards, not just Czech ones.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Habitat loss and cut ecological corridors
Biodiversity net gain, step by stepEcologist-led biodiversity survey → baseline map of existing trees, species and protected species → coexistence and connectivity strategy against the build programme → biotope/species lists → recalculation against the baseline to quantify improvement.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureHabitat loss and cut ecological corridors, Biodiversity net gain, Ecological connectivity
Biogenic carbon is a bonus, not a currencyA kilogram of dried timber holds ~0.5 kg carbon, equivalent to 1.8 kg biogenic CO2, showing as a negative on an EPD. Combining it with fossil emissions is “fundamentally wrong” because it masks inefficiency — he has seen projects 15 years ago deliberately use more timber to make the number more negative.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
Biogenic carbon nets to zero, not minusUnder the current standardised method, sequestered carbon is counted as negative at the start of the life cycle but must be returned to nature in the end-of-life modules — so a timber building does not finish in the negative, it finishes at roughly zero.Expert Open for expert reviewLogistics Development in the concept of certification and LCAEmbodied carbon of new and demolished warehouses, Life-cycle impact by stage
Bioreceptivity belongs to clay, not cementResearch at the faculty explores how algae, moss and living organisms can grow on printed structures, but it is done in clay, described as a much more nature-friendly material for that purpose.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research labHabitat loss and cut ecological corridors
Biosphere is not an externalityShe rejects the three-overlapping-circles model in favour of the “wedding cake” hierarchy: environment is not one competing interest but the context all life and all economic activity sits inside.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Blackout blinds are technically possible and practically absurdAdding internal blackout to a translucent envelope would mean doubling the system across “100 kilometres of line”, doubling price and construction complexity — and in a clean industrial process textiles that collect dust are not allowed.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Visual impact of logistics on neighbours
BMW’s pressure travels down two tiersOn the Hanon project in Kladno (a supplier of cooling devices to BMW), the end carmaker’s electrification and quality demands forced all furnaces and process technology to electricity, PV across the roof including the old structure, heat pumps retrofitted into the existing building, and overpressure zones in finishing areas.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsHigh operational energy demand
BNG used outside Britain, as a design instrumentThe team scored the site’s baseline biodiversity (area, species count, plant age/trunk diameter) against the designed habitats using the British BNG standard.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusHabitat loss and cut ecological corridors, Biodiversity net gain
Boring numbers buy you the joy of lifeThe graphs-and-numbers front end is the price of admission: it is what later creates room for design. Their example of the unformed brief is a client arriving with “we have 2000 employees” and no idea how to divide them into teams.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
Brand trust, not planning gain, is what opens the factoryToday the driver for opening industrial sites to the public is branding — the owner wants the public to be friends with the brand, and the shop front sells the whole brand, not just that factory’s output. There is no legal obligation to open up; it is incentivised, not prescribed.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Closed sites that give little back to the city
BREEAM LCA runs to 60 yearsFor the Greenpoint building in Prague, the BREEAM life-cycle assessment used a 60-year study period, flagged as notably long.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLEmbodied carbon of new and demolished warehouses, Whole-life carbon
BREEAM Outstanding added 4.82% to capital costThe capital cost uplift for BREEAM Outstanding on a large UK warehouse was +4.82 %, and under 0.5 % for Very Good or Excellent.External Open for expert reviewTarget Zero – warehouse study (UK)Designing for an unknown tenant
BREEAM’s warehouse typology is still generic underneathBREEAM does have a dedicated warehouse typology, but it derives from the generic one, so it keeps asking about cycling, biodiversity and user comfort and cannot drop them. Meanwhile SBTool CZ is entering Czech legislation, and banks are beginning to expect it.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
Brewing waste heat heats the public buildingExcess heat from the brew house is ducted to heat the new public building; cold storage adds a heat-pump opportunity. But the transmission distance is limited by temperature: high-grade heat travels, low-grade heat does not.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Waste heat recovery, Heat recovery radius
Bring the client into the iteration, not the resultOn a commercial developer scheme, the brief’s setbacks, height and podium rules were fed into a generative engine; massing options were filtered by daylight, solar, microclimate and view-factor KPIs. The novelty was inviting the client into the process and surfacing KPIs up front.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Brownfield rules block on-site recyclingCzech environmental code for brownfields is stricter than German or English practice, forcing removal and off-site storage of material he regards as safe to reuse in place — costly, and a running argument with authorities.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formEmbodied carbon of new and demolished warehouses, Material reuse share
Brownfields are per mils of the marketHaving built over 1,000,000 m² on brownfields, he still calls brownfield reuse a conference fashion: against total built space it is a fraction of a percent. Both brownfield and greenfield are needed — and he says plainly greenfield “is of course not the ideal solution”.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formLand take of logistics buildings
Build nothing firstFollowing WBCSD’s Halving Carbon Today, the hierarchy starts with demand reduction — build nothing, reassess the need, don’t over-design — then low-carbon materials, then careful use. Industry wants to skip straight to drop-in low-carbon conventional materials, and that path cannot reach the target.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses
Building green on a landfill that vents methaneFælledby sits on a former landfill on Amager; open fire is prohibited because of methane risk, and a clay cap had to be laid over the whole site. The site was also one of the last big green spaces near central Copenhagen, drawing scientific and public opposition to building at all.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Building services are a whole-life carbon sleeperIn Ramboll’s light-industrial/warehouse sample, building services are surprisingly significant on a whole-life basis, because MEP typically has to be replaced once or twice over a building’s life.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses, Life-cycle impact by stage, Whole-life carbon
Buildings have non-human usersA building sits in nature and is inhabited by animals and plants as well as people, so design should actively support those other users.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Buying a building is buying a pig in a pokeThe framing device: acquiring a company or a property is the same act — an enormous sum spent on something whose hidden defects you are trying to mitigate or at least reflect in the purchase price. The Czech version of the idiom uses a hare rather than a pig.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
California wrote the warehouse design codeAB 98 (2024) imposes statewide standards on logistics developments: 50 ft buffers on industrial-zoned sites and 100 ft on non-industrial sites within 900 ft of sensitive receptors; a minimum 500 ft setback for truck loading bays; buffers formed of a decorative wall or landscaped berm 10 ft or more high with two rows of drought-tolerant trees in 36-inch boxes at max 40 ft spacing; loading bays oriented away from receptors; PV plus battery storage, 10% of car stalls with EV charging and 50% pre-wired for facilities of 250,000 sq ft or more; and an approved truck routing plan before occupancy.External Open for expert reviewNational Law Review, 2024Visual impact of logistics on neighbours, Distance to housing, Visual impact on neighbours
Car-free core written into the competition entryAt Sugar Valley the team fixed a car-free core and a central green spine as competition-stage commitments, which then bound the mixed-use programme around it.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureGreen-core anchoring of mixed uses
Carbon has a horizontal biasEmbodied carbon is driven by horizontal elements, because that’s where the mass is. In one Ramboll study structure was ~60% of upfront carbon, and within structure, floors dominated. For logistics — vast ground slabs, vast roofs — the horizontal plane is the whole game.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
Carbon is decided in network design, not in the buildingThe biggest lever is proximity — putting the warehouse as close as possible to demand — but with a real trade-off between many small warehouses and few large ones, which is exactly what the multi-year network model resolves.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentLast-mile delivery emissions and traffic, Delivery catchment
Carbon price is a design input, not an accounting footnoteEmission allowance/offset costs attached to bought heat will rise, as will gas and fleet fuel, so operating cost for a building being designed today “will grow significantly.”Expert Open for expert reviewBeyond the Concrete – Designing Buildings That LastHigh operational energy demand, CapEx–OpEx ratio
Carbon rules are killing basementsStrict CO2 regulation in Denmark has made below-ground structures difficult: timber cannot go in the ground because of rot, and excavating and transporting soil is carbon-expensive. Parking is migrating from underground to above-ground structures.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased BuildingsEmbodied carbon of new and demolished warehouses
Carbon tunnel vision, invertedHe accepts the standard critique that a carbon-only focus crowds out water, health and inequality, but argues the opposite in practice: interrogating the carbon of a material forces you to ask where it came from and where the energy came from, which opens the wider conversation.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and Delivery—
Certificates are a language for banksCertification’s real function is as a common language linking investors, tenants and banks. Banks tie loan volume to rating level: gold unlocks the full sum, silver a smaller one.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
Certification as a recycling driverHe credits BREEAM specifically with pushing industrial buildings toward the highest possible material recycling rates, and says the advantage of industrial buildings is that they are very easy to recycle.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formEmbodied carbon of new and demolished warehouses, Design for disassembly score
Certification as karma and PRBeyond the financing angle, they characterise a large part of green credentialing as company PR — “check out what we did” — with the client effectively buying the problem in order to get some karma for it.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
Certification concept as a red-yellow-green mapAt concept stage the LEED consultant produces a chart splitting credits three ways: green, essentially certain; red, technically impossible (no public transport); and a middle band that will be fought for as documentation deepens.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELL—
Certification is a tool, not legislationThe closing takeaway: certification systems have limits and are not law; resilience is an additional layer; and the decisive input is the designer’s critical thinking.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
Certification is pulled by clients, not pushed by industryRoughly 40 BREEAM certifications in the portfolio, running from building permit through to occupation. He is explicit that certification is not the industry pushing itself — it is client and market demand. The new BREEAM version ties more tightly to EU taxonomy, requires detailed energy management, and bans fossil fuels at the highest rating level.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial Buildings—
Certification of reused structural elements is the real blockerWithout a material passport you must certify each reclaimed element individually before using it structurally; insurers are the other obstacle. A building passport, held in the model, is the fix.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Embodied carbon of new and demolished warehouses, Material reuse share
Certification treats a building as a puzzleCertification does not pronounce a building good or bad; it splits it into pieces (location, envelope, LCA), scores each, and reassembles a comparable total.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
Certified sheds valued 25 bps higherBREEAM-certified logistics assets in the UK and Europe were valued about 25 bps above non-certified ones and let faster.External Open for expert reviewSustainability Unboxed – Delivering on Logistics and Distribution WarehousesGreen valuation premium, Void period
Charging, not the vehicle, is the electrification bottleneckThe main barrier is charging time and infrastructure scarcity causing courier downtime; the NGSeat pilot built a battery-swapping ecosystem around a universal battery usable across more than twenty vehicle types, swapping in under a minute, aiming at up to 90% CO2 reduction, tested with last-mile food couriers.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubsLast-mile delivery emissions and traffic, Last-mile delivery emissions
Checklists invite point-chasing, weighting resists itLEED and BREEAM function more like checklists, so a designer can hunt the highest-scoring categories; DGNB and SBTool recalculate points through weights so the cheapest route to a score is obscured.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
Circulation spaces defended with sensor dataIn the US, public or private funding cannot be sought for undefined space, so a Cincinnati university client attacked the atria, stairs and wide corridors as unfundable. A sensor-and-camera research project recorded how students actually used them, reclassifying them as learning spaces — and during the pandemic it was the only new campus building that still worked.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased BuildingsSocial interaction index
Cities beyond the climate battleWidening Guterres’ line: cities are per se civilisation’s most important transformation tool, not just a climate arena.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
Cities grow while their countries shrinkEven in European countries with flat or declining populations, city populations keep rising, pulled by younger working-age domestic and foreign migration. Warsaw is the extreme case.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Cities outgrow their countries, everywhereOf roughly 1,000 major global cities tracked, around 70% outpaced their national economies in GDP and employment growth in 2025; those cities hold about a third of world population but produce roughly 60% of global GDP, over half of high-income households, and nearly two-thirds of globally ranked universities.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Citizens are the critical infrastructureAgainst the framing that resilience is an energy or data problem, she names citizens as Europe’s most critical infrastructure, and cities as the asset where GDP actually sits.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
Cleaning the harbour was never about swimmingThe real payoff was unlocking old industrial harbour fronts for housing, and turning the water itself into Copenhagen’s largest urban park.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
Client refused to wait 15 years for greenA plant growth analysis defined how far plants could climb in one to five years; the resulting horizontal ribs are planter boxes set at those growth intervals. Species vary by façade orientation.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusHabitat loss and cut ecological corridors, Green plot ratio
Climate risk splits four ways, not twoPhysical risks divided into acute (floods, heat waves) and chronic (rising temperatures, sea-level rise), plus transition risks and opportunities as the second pillar. The classification is lifted from the CSRD directive rather than invented.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Closed-loop water killed by human behaviourA closed greywater and blackwater recycling concept developed with a Swedish partner was dropped because occupants flush cleaning chemicals, T-shirts and worse down warehouse toilets — an unacceptable risk for investor and tenant.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsWater reuse share
Cloud in the city, not in the middle of nowhereThe framing of the whole lecture: data centres should be brought back into cities and treated as part of everyday urban life, rather than exiled to cheap land.Expert Open for expert reviewCloud in the city – data centres, urban development and implications—
CLT was not the goal, it was the outcomePenny never asked for a wooden building; it asked for something cheap, fast and repeatable across a 400-store estate. CLT won because YUAR pushed it as the most viable answer.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itEmbodied carbon of new and demolished warehouses
Community engagement shortens permitting and leasingEngaging communities early and mitigating traffic, pollution and green-space loss builds buy-in and can speed up development and leasing.External Open for expert reviewSustainability Unboxed – Delivering on Logistics and Distribution WarehousesSocial acceptance
Compliance passed by deleting a metre of floorOn the case study, the Czech daylight code was satisfied with almost no design change — a windowsill — plus a redefinition of the assessed zone, excluding the one-metre strip along the building core as circulation rather than administrative work. Described as standard practice.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLDeep, dark and noisy workplaces
Concentration of functions equals freedom elsewhereConcentrating the visitor programme onto one part of the site is what frees the remaining space for vegetation and public function.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Closed sites that give little back to the city, Publicly accessible area
Concrete cannot stop and goPlastic printers retract, travel and resume; concrete cannot, because pressure keeps building in the hose after the pump stops and must rebuild before flow restarts. Discontinuous geometries must be printed in whole sections, and the rough finish is a direct result of the technology.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Concrete is a low-carbon materialPer kilogram, of five compared, steel is highest at ~1.55 kgCO2/kg (range 0.5–3), then mineral wool, then CLT, then plasterboard — and concrete is the lowest. The damage comes from volume, not intensity. He calls a mineral wool factory “like a mini volcano.”Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
Consolidation centres cut trips 20–50%Urban consolidation centres, transferring goods from large vans into smaller cleaner vehicles, are proven to reduce freight vehicle trips by 20–50% in some cases — but effectiveness depends entirely on location and actual usage.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubsLast-mile delivery emissions and traffic, Thomas Olsen, Eva Kažukolovaitė
Construction logistics is planning’s blind spotIt makes up 20–30% of urban freight traffic, involves the heaviest vehicles with disproportionate impacts on congestion, emissions and road wear, is set to grow with urbanisation and renovation, and is nonetheless poorly coordinated and rarely integrated into planning.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubsRoad freight impact
Construction traffic dwarfs parcel trafficLast-mile delivery accounts for roughly 3% of urban vehicle kilometres driven, while construction site logistics accounts for about 37% — yet EU policy and funding attention concentrates on the former.Expert DisputedIntegrated Urban Logistics – From last-mile to mobility hubsLast-mile delivery emissions and traffic
Consumer impatience is a physical planning forceBecause consumers expect near-instant delivery, urgency pushes warehousing closer to demand; goods that can wait one to three days by truck can sit in CEE and still serve Germany, France, Spain and Italy.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentDelivery time
Contrast, not imitation, next to a heritage buildingWhere a preserved solid masonry building meets a new industrial volume, they deliberately based the design on contrast — the new building fully translucent and light despite its size. And the harder case is named: a 30-year-old neighbour has no heritage value to anchor against.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Visual impact of logistics on neighbours
Converting a concrete frame to timber late is a disasterProjects that take a concrete-frame design and try to make it timber at the end produce a timber building everyone hates because it was never designed as one — which then discredits timber.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses
Copenhagen’s bike lanes took decades and cannot be retrofitted cheaplyCopenhagen’s wide, kerb-raised bike lanes are an enabling system built over decades; real accommodation of new last-mile vehicles means widening lanes, and that is not a low-cost retrofit.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubsLast-mile delivery emissions and traffic
Copenhagen’s liveability worth EUR 5bn GDPA Ramboll study claims Copenhagen’s resilience boosted the city’s GDP by 5 billion euro compared with 20 non-resilient European cities.Expert DisputedFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
CSRD is what actually buys the analysisCompanies most commonly commission climate risk assessment because they need compliance — CSRD non-financial reporting — or because a bank/investor requires it before financing.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Cycling credits for a hall in a fieldCycling infrastructure carries substantial points, but a warehouse in the middle of nowhere has no cyclists; the building effectively loses points for a category meaningless in its context. Such criteria should be removable rather than scored.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
Czech benchmarks built from ~117 buildingsUCEEB assembled roughly 117 Czech building LCA case studies and derived preliminary national benchmarks — the quoted 41 figure being the 66th percentile of all values. Explicitly described as a starting point, not a large statistical sample, yet this is how limits and green public procurement thresholds get made.Expert Open for expert reviewLogistics Development in the concept of certification and LCAWhole-life carbon
Czech brownfields are the wrong brownfieldsUnlike Germany, France or Spain, CZ has no stock of 1980s–90s light industrial sheds. Its brownfields are steel mills and heavy factories: hard to convert, too contaminated to clean economically for residential — so most are demolished.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formEmbodied carbon of new and demolished warehouses
Czech fire rules are stricter than the EU’s — and these buildings are changing…Fire regulation in Czechia is described as harder than the EU baseline, with a threshold effect above roughly 850 m² per room; they claim their timber stores are themselves pushing the regulation to change.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itEmbodied carbon of new and demolished warehouses
Czech grid is the real siting constraintA studio participant notes Czech data centres cluster near cities because of grid limitations, and that the de-urbanisation forecast only becomes real once energy and high-speed connectivity are solved. Parker agrees and adds that Central and Eastern Europe are currently in a weaker position on renewables transition than the Nordics or Spain, and should prioritise it structurally so nearby logistics and manufacturing can benefit.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Czech height limits are quietly repelling investmentFully automated warehouses require high-bay buildings (20 m+, up to 30 m). Czech master plans and municipalities effectively don’t approve them; German and British investors know this and don’t even enquire. Poland has just permitted 30 m buildings.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentSpace, energy and labour needs changing with automation, Visual impact of logistics on neighbours, Adam Večeřa
Czech investment volumes are an artefact of illiquidityA reported +250% jump is explained away: the Czech market is dominated by four or five developers such as CTP and VGP who build and hold rather than sell, unlike Panattoni. Two portfolio trades produce a headline spike; this year could be “down 80%“.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Czech legal emission factor is double realityIn one case study, switching to a Norwegian-style green electricity mix roughly halved the carbon footprint versus Czech figures — but she adds that the carbon emission factor written into Czech legislation is about twice the real value, so the modelled impacts are overstated.Expert Open for expert reviewLogistics Development in the concept of certification and LCAOperational carbon
Czech mayors have almost no reason to say yesFor a 40,000 m² occupier with around 400 employees over a 30-year horizon, the municipality itself receives roughly 22 million CZK in Czechia, versus a far larger share in Germany — while national tax revenues are broadly comparable between the two countries.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsSocial acceptance
Czech Republic went first; Germany followedThe CLT store was built in Czechia before the German parent group took the same decision one to two years later.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
Czechia is becoming the storage room for its neighboursCzechia is becoming a storage location for the surrounding markets (Germany, Austria, Switzerland).Expert Open for expert reviewPartner feedback – final review (2026)Land take of logistics buildings
Danish pit-storage heat pumps match warehouse scaleDanish district systems combine large heat-pump units with water-pit thermal storage serving a village or city district; their megawatt capacity is of the same order as a logistics building’s, which is why he reads them as the model for the sector’s future.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsHigh operational energy demand
Data centre carbon is many multiples of a warehouseRamboll’s late-2025 white paper charts a typical logistics warehouse against a data centre; the difference, both operational and upfront, is “many multiples.” Normal building rules of thumb do not transfer.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryOperational carbon
Data centre sizes are commercially opaqueAsked for the minimum viable size or typology of an AI-capable data centre, he admits the data is not available: actual facility sizes and changing capacities are confidential information forecasters cannot access.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Data centres are giant heatersThey must hold ~100% uptime through the hottest summer day, so they need chiller capacity sized for the worst case regardless of waste-heat recovery.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryWaste heat and cooling of data centres, Waste heat recovery, Julia Godard Lombard
Data centres now outbid logistics for land, power and capitalA direct competitor on three fronts simultaneously, expected to intensify. Notably they do not compete for labour.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Data centres outgrowing the FLAP citiesEurope’s data centres clustered in Frankfurt, London, Amsterdam, Paris and Dublin because financial-sector low-latency needs put them there. As AI diffuses beyond finance, demand is dispersing to Madrid, Milan, Vienna, Warsaw and Nordic cities.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Data centres will de-urbanise in 10–15 yearsBeyond the current 3–4 year visible pipeline he expects a de-urbanisation trend: as cloud technology matures and latency constraints ease, data centres move to isolated rural areas where costs are lower.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Data is the foundation of the whole pyramidWithout LCA data you cannot calculate indicators, set limits, attach incentives, or legislate — so databases sit beneath LCA, politics, legislation and finally sustainability. The relevant standards are EN 15978 (buildings) and EN 15804+A2 (products), developed over 15 years.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
Daylight buys 18% productivity, retail 15–40%Same survey as cited: real daylight made workers 18% more productive; retail sales rose 15–40% where people felt better; better lighting plus individual temperature control raised productivity by 23%.Expert DisputedCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLDeep, dark and noisy workplaces, Worker well-being
Daylighting a river that was a technical problemA Singapore project from ~20 years ago reversed a tunnelled watercourse under a park; what was once solved technically now handles storm volumes classical infrastructure cannot, and became a public place people play in.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureStormwater and sealed surfaces on logistics sites
Defence spending exposed roads that can’t carry tanksWhen defence emerged as an economic driver, it was pointed out that many European roads and bridges cannot cope with tanks. He also flags ports as a coming choke point, with more traffic shifting to Mediterranean ports rather than routing round to Amsterdam.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Delivery robots have no legal place in the street sectionAutonomous delivery robots raise an unresolved space-allocation question — sidewalk, roadway, or dedicated robot lanes, which do not exist anywhere in Europe — and the question of who benefits must be weighed before deployment.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubsLast-mile delivery emissions and traffic
Density is the environmental strategyMaximise utilisation of the plot so you do not consume more free space outside the city.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formLand take of logistics buildings, Land take
Design challenges live at the city’s edgesDesigners have concentrated on urban squares and city centres while the genuinely exciting and unaddressed design problems sit at the periphery, where industry and logistics land.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Design for evolution, not for completionBuildings, landscapes and infrastructure should be designed with the ability to transform, adapt and regenerate over time, on the model of living systems.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Design is the only lever architects holdPrintability depends on material, printing parameters, hardware and environmental conditions — none of which architects control — plus design, split into geometry and slicing. Design has the highest impact on printability and is among the easiest factors to modify.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Design teams chase BREEAM credits, not the buildingDesign teams focus on achieving BREEAM credits rather than on the building as a whole.External Open for expert reviewSchweber & Haroglu (2014) – The impact of BREEAM on the design of buildingsHabitat loss and cut ecological corridors
Design’s object is now invisibleBriefs used to be plainly visible; today the design material is hidden knowledge — safety, microclimate, nature.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
Designed in a year, permitted for yearsTheir most troublesome project has a facade of perforated steel mesh carrying the tread profile of a Continental tyre, with six towers hidden behind the walls. The design took one year; the building permit has been running for years, blocked by a single difficult neighbour.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itVisual impact of logistics on neighbours
Designers must stand in the field of conflictShe defines the designer’s job as navigating conflicting requirements and owning the imperfect decision.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Designers turned a blind eye to logisticsThe profession’s “blind belief in technical solutions” meant infrastructure, industry and logistics were never treated as a design challenge at all.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Developer margins of 3–5%Developer margins on logistics projects are around 3–5 %.Expert Open for expert reviewPartner feedback – final review (2026)Designing for an unknown tenant
Developer money into forest resilienceA net-zero pilot on the Škoda Transportation brownfield (a site that took ten years to unlock) is paired with private investment into Czech forests for resilience and CO2 capture — claimed as the first of its kind in CZ.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
Developers overbuilt, then vacancy caught themThe sector overshot: developers could not keep pace with pandemic demand, then “overstepped or they overbuilt,” pushing vacancy up. He points to the lag between demand and delivery.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Difficult ground can decide your carbon scoreIn that house, difficult ground conditions forced foundations about 1.5 m deep; the concrete became the single biggest hotspot in the whole LCA, outweighing every above-ground material choice. It raises the question of whether uniform carbon limits are usable for every site.Expert Open for expert reviewLogistics Development in the concept of certification and LCAEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
Digging materials up costs more than buying newThe economics of reclaimed material fail because extraction from an existing building can be more expensive than new supply — which is exactly why you design for disassembly now.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Embodied carbon of new and demolished warehouses, Design for disassembly score
Digital models are not yet market standardHVAC designers still size systems from codes and standards alone, with the simplifications that implies; detailed energy modelling has to be brought in deliberately, project by project.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial Buildings—
Distant material extraction damages distant biotopesSourcing from far away harms the biotopes at the extraction site and adds transport CO2, which is an argument for site-derived materials — though she notes the Bestseller site is “probably just sand,” ruling out rammed earth there.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureEmbodied carbon of new and demolished warehouses, Biodiversity stress from materials
Don’t dig down vs biodiversityConfronted with the previous lecturer’s carbon rule against excavation, she concedes it is right on carbon alone, then argues the counter-case: sinking a structure yields a large permeable soil surface that handles rainwater.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureStormwater and sealed surfaces on logistics sites, Impervious surface ratio
Don’t force the wrong second life on a buildingFor data centres he would not compromise operational efficiency to reuse a shell: a 10%-less-efficient data centre likely loses over its life. His preferred move is relocation, not demolition — put the data centre elsewhere and give the existing building a use it suits.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses, Whole-life carbon, Julia Godard Lombard, Katrin Rybinskiy
Don’t get obsessed with the 10%She pushes back on her own metric: the essential shift is telling a story about nature from the outset; the number is a support, not the point.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureBiodiversity net gain
Don’t let every unit be 2,000 m²Mix rental unit sizes and price points deliberately, so a 50 m² yoga studio sits alongside large tenancies — this is what varies opening hours and offerings across the day.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient NeighborhoodsMixed-use ratio, Marek Nový
Dublin planned for data centre demand instead of reacting to itDublin integrated data centre demand into its forward energy and land-use planning alongside hospitals, schools, housing and offices, deliberately steering the facilities into a chosen part of the city — the opposite of developers buying whatever plot they could find. He calls urban planning a fundamental and badly underused tool in Europe.Expert Open for expert reviewCloud in the city – data centres, urban development and implications—
E-commerce is not the main occupier — and is shrinkingPure-play e-commerce fell from about 17% of European take-up in 2021 to about 8% in 2025. Online penetration peaked at roughly 15–25% of retail sales (up to ~35% in the UK during the pandemic) and has since fallen back and levelled off.Expert DisputedPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Each IT generation makes the building hotterEvery new generation of chips is more powerful and therefore produces more heat, so the cooling load keeps escalating even as the buildings grow — which explains why the efficiency curve flattened.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsWaste heat and cooling of data centres, Power usage effectiveness
Easier to drill wood than reinforced concreteAdaptability argued at the most practical level: a timber building tolerates late changes in a way reinforced concrete does not.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itBuildings that change slower than logistics
Efficiency has hit a plateau at 1.5PUE dropped sharply about 15 years ago (~2.5 in 2007) but has stalled around 1.5 for the last six or seven years, against a theoretical ideal of 1. Individual projects can go below 1.5; the industry collectively is struggling to improve.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsWaste heat and cooling of data centres, Power usage effectiveness
Eight degrees quintuples walking distanceOn Singapore’s North-South Corridor — an eight-lane traffic corridor becoming ~25 km of new urban development — a deliberately low-tech urban cooling toolbox targets an 8°C drop in perceived temperature; that drop multiplies comfortable walking distance by five.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient NeighborhoodsWind, heat and missing shade around large buildings, Thermal comfort, Tree count and canopy cover
Electric trucks as a noise-permitting instrumentRaised as an open design question: as electric trucks replace diesel, the change in noise levels could alter what is permissible near cities.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsVisual impact of logistics on neighbours, Noise level
Electric trucks don’t buy you a green corridorAsked whether electrifying fleets enables green corridors, she says it probably makes no difference: the corridor problem is spatial, not fuel-based.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Electrification is a system shift, not a vehicle shiftSwitching fleets to electric requires charging stations, battery swapping and grid capacity designed into streets, logistics hubs and buildings, forcing coordination between transport planning, energy planning and urban development.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubsLast-mile delivery emissions and traffic
Electrification may shrink automotive storage demandGerman automotive manufacturers have historically stored large volumes of combustion-engine parts; a simpler electric drivetrain implies less parts storage.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Electrifying the car is the lazy answerManufacturers respond to one person in a fossil car by making the hardware better; the flexibility strategy is putting five people in it. Better hardware versus better utilisation.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient NeighborhoodsSpace utilisation
Emptying bins that aren’t fullThe ROSE project replaced fixed collection schedules with sensor-based fill-level clustering, vehicle assignment and dynamic routing, piloted in Montana (Bulgaria) and Cascais (Portugal) — showing even highly standardised public services carry large hidden inefficiency.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubs—
Enabling development as an inherited burdenMunicipalities routinely require the incoming developer to build infrastructure sized for other, unrelated parts of the city, on top of remediation costs.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
Energy chapter is half of a LEED GoldLEED Gold requires at least 60 credits; the energy and atmosphere chapter carries 33 credits, roughly half of a Gold on its own — and it is the chapter that forces detailed dynamic simulation, making it time-consuming for the consultants.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLHigh operational energy demand
Energy data collected like rentLeading owners treat energy data and energy certificates as a core asset KPI, collected with the same routine as rent and occupancy.External Open for expert reviewSustainability Unboxed – Delivering on Logistics and Distribution WarehousesWhole-building energy data coverage
Energy is 1% of a company’s budgetFor a typical office, retail or shopping-centre operator, energy costs are around 1% of the overall company budget, which is why owners are not strongly motivated by energy-efficiency measures; the people-related metrics move the budget far more.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLHigh operational energy demand
Energy performance is a financing instrumentEvery project carries an EPC that must be shown to banks and investors; landing below a threshold value buys better financing terms.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsEnergy use intensity
England’s best farmland is going a hundred times fasterCPRE research found nearly 14,500 hectares of England’s Best and Most Versatile agricultural land lost to development since 2010, with the annual rate rising from 60 hectares in 2010 to over 6,000 hectares by 2022 — enough land to grow at least 250,000 tonnes of vegetables a year, while 26,000 hectares of brownfield sat available.External Open for expert reviewCPRE, 2022Land take of logistics buildings
ESG entered the risk register only ~2 years agoESG is described as the pillar “gaining more traction in the market in the last, I would say 2 years,” slotting alongside financial, market, legal, IT/cyber and HR risk — with the environmental leg mapping directly onto buildings.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
ESG survived the politics, via the banksDespite political retreat from environmental commitments, the rules and financial plumbing still embed it: banks and regulators build climate and ESG factors into lending decisions, which determines project funding and where money flows into cities.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
EU taxonomy – not mandatory, but at the end it isFormally voluntary, yet without it financing is effectively unobtainable. In practice it means blower-door testing and thermal imaging for envelope integrity, full LCA covering embodied plus operational carbon, and a high-grade BMS — and these KPIs now sit inside the general contractor’s contract.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsWhole-life carbon
Europe finally has a soil lawDirective (EU) 2025/2360, the first EU-wide Soil Monitoring Law, was agreed in April 2025 on the finding that over 60% of EU soils are unhealthy. It obliges member states to monitor soil health on a common methodology and to apply mitigation principles for soil sealing and soil removal in spatial planning — but the 2050 healthy-soils goal remains non-binding.External Open for expert reviewCouncil of the EU, 2025Land take of logistics buildings
Europe is behind the US and China on deploymentShe distinguishes Europe’s level of testing and piloting from actual deployment and concedes a big gap versus North America and China on autonomous urban delivery, attributing it to fragmented national and regional regulation, the geography of many adjacent countries, and differences in governmental support and funding.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubs—
Europe seals 1.5 km² of land every dayNet land take in EU cities and their commuting zones ran at 540 km²/year in 2018–2021, up 32% on the 410 km²/year of 2012–2018. Most of it comes off arable land (268 km²/year) and pasture (182 km²/year). To hit “no net land take by 2050” Europe would have had to cut this by roughly 27 km² every year from 2022 — it is going the other way.External Open for expert reviewEuropean Environment Agency, Net land take in cities and commuting zones, 2024Land take of logistics buildings, Land take
Europe’s urban share is halving by 2050Europe’s major cities produced just under a third of global city GDP in 2000, just above 20% by 2025, and modelling puts it near 15% by 2050 — Europe still growing, but far slower than China, India and Asia-Pacific.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Even the investors are asking whether AI use will changeAt a London conference days earlier, very large investors were questioning whether the current pattern of AI use — and therefore the infrastructure it demands — will persist; the industry has no answer.Expert Open for expert reviewCloud in the city – data centres, urban development and implications—
Every surface recruited – wetland, roof meadow, green facadeThe landscape is staged as a sequence — arrival through forested landscape, open wetland that also handles rainwater, a large roof meadow for workers’ lunch breaks — with roof and facade both counted as biodiversity surface.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureHabitat loss and cut ecological corridors, Function stacking index, Green roof coverage
Every version makes yesterday’s exemplar mediocreČSOB SHQ was certified under LEED v3; v4/4.1 are current and v5 was expected mid-year. Newer versions are stricter on most credits, so the same building assessed today would score substantially fewer credits despite still being top property in the country.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELL—
Everyone is a carbon assessorAssessment splits into designer-level (fast, rough, decision-driving), discipline-level, and professional/codified — and speed matters as much as rigour.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and Delivery—
Exit-grade quality is enforced by the fund, not the codeBecause each asset must survive comparison with the whole European market and pass multiple due diligences on sale, the investor exit drives build quality upward.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
Expandable units are wanted but planning kills themExpanding means either a two-to-three-year build-and-permit process or waiting for a neighbour to vacate. The workaround the market uses is outsourcing to 3PLs during growth.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performanceBuildings that change slower than logistics, Adaptability, Amy Naprstek
Exposure is easy; vulnerability is the design questionExposure is “really easy to calculate” from location and hazard data, but vulnerability depends entirely on what adaptation measures are already built into the design or in operation.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Facility managers inherit a building blindA frequent failure: the building is built, property management arrives, but never receives sufficient as-built documentation, and the information about settings, regulation and measurement systems is simply lost. Handing that data over is itself part of commissioning.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELL—
Fælledby outcome numbersComputational optimisation is credited with delivering, for ~5,000 new residents: 25% with direct access to nature, 30% with a view to the park, 100% with a view to green areas, and a balcony for everyone.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
False precision is nonsenseA figure quoted to three decimal places is meaningless. Uncertainty is inevitable; what matters is being transparent about its sources (project maturity, quantity data, carbon data).Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon intensity
Farmland bans are the engine of brownfield revivalEuropean countries are increasingly restricting warehousing on fertile arable land, in some places outright, pushing developers toward brownfields. Old steelworks and contaminated production sites in CEE are being demolished and converted to small business units serving inner-city demand.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentLand take of logistics buildings
Fastest-growing segment in real estateRoughly 11,000–12,000 data centres exist globally, consuming about 1.5–2% of the world’s electricity and accounting for somewhere in the region of 1–3% of global CO2; the market is estimated to grow 16% per annum to 2030.Expert DisputedCloud in the city – data centres, urban development and implications—
Fewer than 5% of UK industrial roofs have panelsUnder 5% of UK industrial and commercial rooftops carry PV. The blockers are structural (~20 kg per panel on lightweight decks), contractual (10-year industrial leases against multi-decade solar assets, with tenants responsible for the roof), and infrastructural — UK government reporting cites grid connection waits of up to 15 years, with the queue growing tenfold in five years.External Open for expert reviewEQT, Why it’s so difficult to put solar panels on warehouse roofsHigh operational energy demand, Rooftop PV generation, Structural utilisation
Fire isn’t timber’s real problem — acoustics isIn their mass timber practice, moisture is manageable and fire is not the biggest issue; acoustics and vibration are. Concrete toppings are added for thermal mass and acoustic/vibration control, not for structure.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased BuildingsEmbodied carbon of new and demolished warehouses
First CEE timber warehouse permit — and unsellablePanattoni were first to obtain a permit for a 40,000 m² warehouse with a timber roof structure in Czechia/CEE. The candid admission: the price is currently so high that building it and selling it to a client is almost impossible.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsEmbodied carbon of new and demolished warehouses, Construction cost
Fit-out can cost more than the buildingIn technically advanced warehouses the internal fit-out (automation, racking, robotics) often costs at least as much as the shell, and frequently significantly more.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performanceSpace, energy and labour needs changing with automation, Construction cost
Five years of continuous supply-chain shockCOVID, nearshoring, inflation, the current oil crisis and the Suez blockage have hit in succession; each pushes companies toward relocating production and storage closer to consumers, and toward decentralisation.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
Flexibility is time, not just hardwareDesigning changeable systems is only the “hardware side”; the robust strategy is spatial quality good enough to host a school, apartments or offices in succession, plus temporal flexibility — public access to buildings standing empty most of the day.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient NeighborhoodsBuildings that change slower than logistics, Closed sites that give little back to the city, Adaptability, Elsa Hauksdottir
Floor-area definitions move your number 5–20%Dozens of incompatible floor-area definitions worldwide (inner face, outer face, midpoint of wall; corridors in or out). The choice alone shifts a kgCO2/m² figure by 5 to 20%, before any design change.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon intensity
For Czechia the risks are drought, floods, precipitationCiting the Ministry of Environment: the biggest climate risks for the Czech Republic are drought, floods and precipitation.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That LastStormwater and sealed surfaces on logistics sites
Forecast – 9% unlevered, 13–15% gearedPrime European logistics returns of ~9% per year unlevered over five years, rising to 13–15% with gearing, on vacancy falling to ~4% and rental growth of ~2–2.5% a year — well below the 2021–25 run of up to 10% a year in the UK and 9.5% in Czechia.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Forklifts, not robots, forced the concretePhase-one capacity leaves part of the terminal unautomated, running manual racking and forklifts; point loads of ~6 tonnes through the wheels made timber structurally unreasonable there. Elsewhere the timber slab still needs a concrete topping; offices keep bare timber.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusEmbodied carbon of new and demolished warehouses, Structural utilisation
Foundation ownership as the reason for the opennessHenning Larsen sits inside the 18,000-person Ramboll Group, which is foundation-owned: profits flow back to humanitarian and research grants, which is what funds the Open Details platform and the research programme.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Four coping strategies, including doing nothingRisk responses: accept and do nothing (a legitimate strategy in some cases), transfer to another party, mitigate, or insure.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Four habitat types as design vocabularyWetland, forest, moorland, green façade — each deployed where it did double duty: wetland beside the truck yard, forest wrapping the car park, moorland meadow across the terminal roof, green façade on the high bays.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusHabitat loss and cut ecological corridors, Function stacking index
Four pillars, with location as the fourthSBTool CZ scores environmental, social and economic pillars plus a fourth — location: public transport connection, what is in the surroundings, whether a car is needed. Named as the distinguishing feature versus LEED and BREEAM.Expert Open for expert reviewLogistics Development in the concept of certification and LCAPublic transport accessibility
France already legislates when your yard lights go offThe arrêté of 27 December 2018 requires interior and facade lighting of non-residential premises to be switched off one hour after occupancy ends or by 1am, whichever is earlier, and not relit before 7am; uncovered car parks must go dark two hours after activity ends. It caps correlated colour temperature at 3000 K (2400 K in nature reserves) and upward light ratio below 1%.External Open for expert reviewMinistère de la Transition écologique, arrêté du 27 décembre 2018Visual impact of logistics on neighbours, Habitat loss and cut ecological corridors
France maps its ecology before it maps its plotsThe Trame verte et bleue, established by the Grenelle 1 (2009) and Grenelle 2 (2010) laws, obliges regions to identify ecological continuities — reservoirs and corridors, terrestrial and aquatic — in their SRADDET schemas, which then cascade into municipal PLU/PLUi plans; the 2021 climate law made ecological-continuity assessment mandatory in local planning documents.External Open for expert reviewMinistère de la Transition écologique, Trame verte et bleueHabitat loss and cut ecological corridors, Ecological connectivity
Free night cooling is still the cheapest moveBefore any mechanical system, the stack effect remains the first and cheapest ventilation strategy: open high and low, purge the building overnight, then hold the cooled air.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLHigh operational energy demand, Natural ventilation potential
Free tool, 15–30 minutes, no registration for the basicsR4RE (“resilience for real estate”), a French platform they discovered “like a month or two ago”, is free for the basic exposure/vulnerability diagnosis and measure list, needs no registration at that level, and takes 15–20 (max 30) minutes. Simulations and adaptation planning sit behind a paywall — with the aside that asking the sales team for a demo yields roughly 30 days of full access.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
From ~12 to 6.6 kg CO2e per m² per yrThe figure fell through roughly 8.9 at tender to about 6.6 once generic EPDs were replaced with specific ones.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
From 1% public to 30% public, plus 20% more greeneryThe brewery project measured its own impact as a KPI: the site went from 1% public to 30% public area, with around 20% more greenery added.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Closed sites that give little back to the city, Publicly accessible area, Green area ratio
From 20,000 households to a countryAn average conventional data centre equals roughly 20,000 households; a hyperscale one about 100,000; the largest under construction as of late last year the equivalent of 2 million households; the largest announced, 5 million households.Expert Open for expert reviewCloud in the city – data centres, urban development and implications—
From 22 certified projects to over a thousandIn 2012 Czechia had only 22 certified projects; by early this year there were more than 1,000 LEED, BREEAM and WELL certified buildings — against one or two DGNB buildings in the whole country. The 2008 ČSOB North HQ is named as the break point.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELL—
From near-bankrupt to global benchmark in one generationIn the 1980s Copenhagen had 18% unemployment, heavy pollution and near bankruptcy. The point is not that everyone should copy Copenhagen but that systemic urban change is demonstrably possible within a generation.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
From static curb allocation to dynamic curb managementCurb use should shift from fixed designation to time-based reallocation (delivery in the morning peak, then parking or public space afterwards), supported by digital booking, pricing and enforcement; curb inefficiency degrades the whole transport system.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubsLast-mile delivery emissions and traffic
Full automation would need power plants bigger than the logisticsPushing warehouses to drone-and-robot-only operation is self-defeating in energy terms: the computing infrastructure required would demand power plants and data centres larger than the logistics facilities they serve.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itSpace, energy and labour needs changing with automation, Level of automation
Fully built, barely usedThat same fully electrified plant is currently running at roughly 20–30% of production with all technology already installed and waiting.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial Buildings—
Gas kept only as an emergency lineOn the newest projects: ZF in north Czechia fully electric with heat pumps and large PV and no gas at all; on another project gas exists solely as emergency backup — plus carbon compensation through credits arranged with a local forest owner.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsHigh operational energy demand
Generic data early, EPDs lateGeneric data (aggregated, e.g. a 90th percentile of specific datasets) belongs at concept stage when the actual products are unknown; EPD-derived specific data belongs once products are chosen. Differences between producers are large and trace back to their technologies and fuels.Expert Open for expert reviewLogistics Development in the concept of certification and LCAEmbodied carbon intensity
Generic EPDs first, product-specific later, contractually lockedLCA ran through every design stage using the 2015-generation Danish method alongside BREEAM. Early stages used generic/average EPD data; high-impact materials were swapped to product-specific EPDs, and those products became a binding requirement in the contractor’s tender.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
Geopolitics assigns tenants to countriesChinese EV manufacturers and suppliers are clustering rapidly in Hungary and Slovakia — the “friendly countries” — while he receives almost no Chinese enquiries for Czechia, Poland or Germany. Separately, Western investors routinely instruct him to present only Czech locations and explicitly refuse Slovakia and Hungary.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
Germany lost the high value, not just the lowBeyond low- and mid-value production moving to China and India, Germany has lost ground in higher-value advanced manufacturing — automotive, machinery, electronics and engineering supply chains. Munich, Stuttgart and northern Italy show declining output.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Germany’s answer – trade tax plus designated landSarah Friedrich explains the German counter-model: municipalities earn trade tax from logistics assets they host, and planning designates areas that must be made available for industry.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial Buildings—
Give nature a lawyerShe points to New Zealand and indigenous legal traditions where nature is granted standing and representation, so it can be a party to a lawsuit.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Give the unloved leftover land to the data centreA Ramboll architects’ proposal puts a data centre in the residual space between motorways: noisy, poorly accessed, effectively undevelopable for anything else — and therefore, he suggests, a place where this programme could go.Expert Open for expert reviewCloud in the city – data centres, urban development and implications—
Glare is judged at the single worst seatSpatial daylight glare and daylight glare probability are both evaluated annually and only for occupied hours, and the analysis is run at one critical point deliberately chosen as the worst case — typically on the south facade.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLDeep, dark and noisy workplaces
Glulam on every unit, a first for Irish logistics parksNexus is the first logistics park in Ireland to offer glulam as an option on every unit.External Open for expert reviewIPUT, Nexus Logistics Park websiteEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
Glulam spans like steel, as the developer puts itGlue laminated timber delivers the same strength and spans as steel.External Open for expert reviewIPUT, Nexus Logistics Park websiteEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
Going above the traffic, not through itThe USafe project answered emergency congestion delays not with faster ground vehicles but hybrid electric/hydrogen drones plus air traffic management, piloted in Zaragoza and Tartu — reframing logistics innovation as urban resilience and adding an aerial layer to the urban logistics system.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubsLast-mile delivery emissions and traffic, Johannes Berger
Green roofs are a biodiversity investment, not a carbon oneThey don’t help with carbon, and on a single-storey large-span logistics roof the added mass would massively increase structure. They make sense where column centres are narrow or the building is already multi-storey. The reframing: if you double the structure to carry the roof, what habitat was destroyed to win that material?Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryHabitat loss and cut ecological corridors, Green roof coverage, Structural utilisation, Biodiversity stress from materials, Ece Yasar
Green roofs are not a substitute for groundA systematic review of 77 peer-reviewed studies found species richness consistently higher at ground-level sites than on roofs for fungi, birds, bees and other arthropods, and concluded plainly that “green roofs should not be used as a substitute for other green spaces.” Substrate depth was the dominant design variable — deep substrates raised plant and arthropod richness across 11 studies, with at least 15 cm needed for overwintering insects — while greater building height reduced spider and vascular plant richness.External Open for expert reviewKnapp, Schmauck & Zehnsdorf, Sustainability 11(20) – 5846, 2019Habitat loss and cut ecological corridors, Green roof coverage, Native species richness
Green roofs vs LCA — an admitted conflictPutting nature on a roof adds substantial structural load, which worsens the carbon calculation; she names this as a genuine conflict.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureEmbodied carbon of new and demolished warehouses, Green roof coverage, Structural utilisation
Greenfield today, city tomorrowEven a greenfield site may become part of a future city; a building that does not contribute to urbanism now “might already be set up to failure in the future.”Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’—
Grey space – buildings sized for Black FridayOccupiers deliberately hold slack — running at maybe 50–70% utilisation for most of the year so they can hit 100% from September through Christmas. Buildings are therefore dimensioned for an annual peak, and this slack is nearly impossible for outside advisors to measure.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performanceBuildings that change slower than logistics, Space utilisation, Elsa Hauksdottir
Grid capacity becomes a planning constraintFor planners the question is not just siting but whether local energy systems can support data centres sustainably — including whether they squeeze residential and commercial supply in the same city.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Grid decarbonisation is the one win happening without usThe last 10–20 years of grid decarbonisation and renewables rollout is the largest impact achieved, and is effectively happening in the background.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and Delivery—
GWP is heading into the statutory energy certificateHe expects global warming potential to become part of the next version of the legally mandated energy performance certificate, meaning embodied carbon would be calculated as part of the ordinary building permit process rather than voluntarily.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
Habitats copied from the surrounding landscape, not inventedThe introduced biotopes deliberately mirror surrounding landscape types rather than importing exotic planting — “not about introducing a tropical garden” — so the design reinforces the nature already present.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureHabitat loss and cut ecological corridors, Native species richness
Half a billion euros of technology under one roofThe newly handed-over H&M automated distribution centre is the largest building in Czechia at 210,000 m² under one roof, multi-storey, targeting BREEAM Outstanding — with roughly EUR 500 million invested in the tenant’s technology alone.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formSpace, energy and labour needs changing with automation, Level of automation
Half of loading zones misusedAround 50% of loading zones are used incorrectly, and cities still rely on manual, reactive patrol-based enforcement; the Smart Zone Enforcement pilot in Bucharest and Istanbul combined sensors, digital booking and an officer app to alert on violations instead of random patrolling.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubsLast-mile delivery emissions and traffic
Harder to design a Penny than the Dancing HouseA signature building can invent its own story afterwards; a discount supermarket is fully constrained by regulation, corporate design rules and marketing.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
He opens by disclaiming the disciplineI’m an economist, I’m not an architect, so I’m not smart enough to do this degree.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Height buys efficiency and buys a fire problemGoing taller improves automation efficiency but triggers in-rack sprinklers, ventilation and exhaust systems. Fire suppression is “super expensive”, so there is a trade-off.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentSpace, energy and labour needs changing with automation, Construction cost
Hidden trade-offs are built into scoringChasing points can produce nonsense on a building: a measure that gains points in one criterion can do harm elsewhere.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
High energy costs are deindustrialising EuropeEuropean energy prices were already above the global average before the Russia–Ukraine war; sustained high costs raise production costs, cut competitiveness and push new capacity to lower-cost regions, hitting energy-intensive automotive and chemicals hardest.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Hiring shifts from drawing to narrativeAI changed what the studio recruits for: less pure architectural production, more the ability to build a narrative, find the right data and story, and spend time on site with people.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Honest gap – valuing nature awaits better toolsAsked how to calculate carbon and runoff performance of a designed ecosystem, she declines to claim expertise and says she hopes emerging AI-based programs will help.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
House prices +90%, incomes +10%Indexed to 2015, European house prices are up nearly 90% (and expected to hold ~90% above 2015 levels by 2030) while household disposable income rose only around 10%; rents show a similar divergence.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Houses lose kilowatts, warehouses lose megawattsLarge volumes, extreme ceiling heights and steep vertical temperature gradients make ventilation, cooling and heat-pump design “a completely different game” from housing.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsHigh operational energy demand, Heating energy demand
How Much Does Your Building Weigh, Mr. FosterHe recommends the documentary How Much Does Your Building Weigh, Mr. Foster as the question of building resourcefully: the more a building weighs, the more trucks it takes to build it.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics Campus—
Hub placement decided without dataCities typically lack visibility into logistics flows and make hub siting decisions without appropriate data; the LogiHub project built a planning platform fusing mobility data with spatial data (loading zones, warehouses, infrastructure) to identify optimal hub locations — a design tool, not a building.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubsLast-mile delivery emissions and traffic, Delivery catchment, Roshni Basu
Hub siting is still trial and errorWhere to place a consolidation hub is an unresolved trade-off between operator cost efficiency and the availability of good space, and cities are learning by doing.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubsLast-mile delivery emissions and traffic
Humans off the top of the trianglePeople should no longer sit at the apex of the hierarchy but inside a circular system, with the mobility system and the nature system driving the plan; a hybrid of the European perimeter block and the village typology produced a dense U-shaped block type.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
Humidity, not Celsius, is the barrierThe walkability problem in tropical growing cities is not temperature alone but humidity — and growing cities worldwide are now generating their own accelerated local climate.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient NeighborhoodsWind, heat and missing shade around large buildings, Thermal comfort
Hybrid work has broken the desk countAttendance peaks Tuesday–Thursday at around 80% and collapses to about 20% on Monday and lower on Friday: 800 employees no longer means 800 desks, and the recovered area goes to green space, fitness and amenity.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
Hyperlocal and citywide, bothNeighbourhoods need functions for residents and destinations that pull in the whole city; other recommendations include slow-pace mobility with very small plazas, aligning placemaking with municipal planners for a mutual business case, defining KPIs for activities, and innovative ownership models for ground-floor space.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
Hyperscale data centres skip Czechia for lack of powerData centres count as an industrial use but are not yet tracked in the sector’s shared research data. Enterprise-scale facilities need to sit near population centres; hyperscale ones are not coming to Czechia because the energy supply isn’t there.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentKatrin Rybinskiy, Julia Godard Lombard
I don’t want to be too romantic about itShe interrupts her own praise to insist the building is a logistics centre with a client programme: traffic and goods flow must work.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
If cities don’t plan for logistics, logistics takes spaceUrban consolidation centres need land inside or at the edge of the city; failure to zone for it does not make the demand disappear, it makes it appropriate space opportunistically and inefficiently.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubs—
In a data centre the embodied carbon is in the pipesFor a typical office, a bit more than half of embodied carbon sits in sub- and superstructure. For a data centre the building fabric is “not that big of a concern” — the mechanical, electrical and plumbing systems dominate, which means the levers sit with equipment manufacturers, not just architects.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
In the forest you must be different; in the city you can matchA factory in a forest has to look completely different; this one, sitting beside panel housing, “looks the same” and therefore makes no violent attraction.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Visual impact of logistics on neighbours
In-city logistics is a separate typology with separate rulesUrban demand is served by “small business units” (SBUs) — pharmaceutical, food, one-hour delivery — sited on brownfields, commanding much higher rents on shorter leases, increasingly let to family businesses and e-commerce start-ups. Some developers call them “sticky boxes.”Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentLindsay Daphne Macuja
Industrial sheds as 4th-generation district heating nodesWith coal-based first-generation district heating closing, industrial buildings — data centres above all — are positioned as crucial waste-heat sources for 4th and 5th generation district heating and cooling networks now being re-mapped city by city.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsWaste heat and cooling of data centres, Waste heat recovery
Innovation blocked by missing regulation, not missing technologyRegulation for a four-wheel electric scooter did not yet exist in all the countries where Green Dash operated: new vehicle types require the regulatory category to be created in parallel.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubs—
Innovations fail from missing support, not bad ideasThe mid-stage (TRL 5–7) real-world testing phase is where most solutions die — pilots demand city access, stakeholder coordination and money — and even proven TRL 8–9 solutions struggle to scale because each city has different regulations, infrastructure and stakeholders.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubs—
Insulation was solved conventionallyPrvok’s walls were printed as an inner and outer leaf with sprayed foam insulation in the cavity, giving thermal characteristics comparable to a regular contemporary Czech house.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Investment agencies as a competitive instrumentAgencies such as CzechInvest exist to attract new business with tax benefits, labour support and permitting help; he rates CEE as doing infrastructure and incentive support markedly better than Western Europe.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
Investment is a EUR 40bn market, three-quarters EuropeanEuropean logistics investment ran at about EUR 40bn in 2025 (down ~3%), against a peak of ~EUR 60bn. Roughly EUR 30bn of the 40 is domestic or intra-European — unusually high versus the normal 60–65% — with almost nothing from Asia, the Middle East or Africa.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Investor speed was a design variableThe first North Harbour neighbourhood was delivered within eight years; investors’ ability to move fast is credited as part of the transformation.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
Investors chase tenant credit and forget the locationAssets bought for long e-commerce leases are now being re-examined: buyers over-weighted tenant credit and under-weighted where the building stood.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Investors hunt the cheapest creditsWhen an investor pursues certification to obtain better banking conditions or resale terms rather than to occupy the building, the behaviour changes: the search is explicitly for the easiest available credits.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELL—
IPUT parks let at about 10% above a typical unitIPUT’s Dublin parks achieve a rental premium of about 10 % above a typical warehouse unit.External Open for expert reviewIPUT – PERE interview with Niall GaffneyGreen rent premium
Island methods travel badly to Central EuropeBREEAM’s approach to landscape reflects England: a small island without large expanses of nature. DGNB, developed in Central Europe, embeds different landscape assumptions.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
Italy’s warehouses eat 432 hectares a yearISPRA’s 2025 land-consumption report records Italy artificialising 2.7 m² per second, 83.7 km² in 2024 — the worst year in twelve. Logistics areas alone grew by 432 hectares in that year (Emilia-Romagna +107, Piedmont +74, Lombardy +69). Cumulatively, logistics consumed 5,104 hectares between 2006 and 2022, and in 2022 accounted for 7% of Italy’s entire net land consumption.External Open for expert reviewRenewable Matter on ISPRA 2025Land take of logistics buildings, Land take
Keep every drop on siteStormwater strategy: nothing leaves the locality, even where legislation would allow it. On a site this size that means thousands of cubic metres — handled through a cascade of four ponds (sediment, stabilisation, then infiltration), and only then technical solutions such as injection wells. “Start with nature and then go with it.”Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Stormwater and sealed surfaces on logistics sites, Stormwater runoff reduction, Stormwater retention volume
KPIs as client-facing argument, not paperworkData and KPI analysis are described as a way to enforce design excellence internally and open dialogue with clients.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Labour costs five to seven times the rentRent is about 5 % of supply chain costs; labour costs $5–7 for every $1 of rent.External Open for expert reviewPrologis – Unlocking Supply Chain Value (2018)Labour-to-rent cost ratio
Landlords want frictional vacancy on purposeInvestors would ideally hold 97–98% occupancy rather than 100%, because a little “frictional vacancy” is what lets existing customers expand in place.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Landscape architecture’s field has been rewrittenOver the last 10–20 years the discipline expanded from parks, playgrounds and urban realm into climate adaptation, rainwater management, biodiversity strategy and green infrastructure — a shift she credits partly to European regulation.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Landscape drove the mobility plan, not vice versaBreaking the runway into small neighbourhoods separated by green fingers and converting the runway into public space gives a maximum five-minute walk to a park; green access within ~300 m is cited as a strong liveability driver, and the landscape strategy shaped the 15-minute framework.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
Last mile is shortest but costliestThe final delivery leg represents 40–60% of total delivery cost while being the physically shortest segment of the chain.Expert DisputedIntegrated Urban Logistics – From last-mile to mobility hubsLast-mile delivery emissions and traffic, Last-mile delivery cost
Lease cycles make the market a slow-moving vesselBecause tenants are locked in, even a violent shock takes years to change the built landscape. Consumers feel price effects in months; the industry adjusts in two to three years.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
Lease length is the hidden design briefLogistics tenants sign 5–7 year leases; manufacturers sign 15, and increasingly 20–25 years, because relocation costs are prohibitive.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentBuildings that change slower than logistics, Amy Naprstek
LEED supplies the ceiling the code lacksWhere the national standard has no upper bound, LEED’s Useful Daylight Illuminance (work surface, around a 3,000 lux upper limit) and Annual Sunlight Exposure (floor-measured, 1,000 lux exceeded for more than 250 hours a year, expressed as a percentage of area) do — and ASE counts only areas actually intended for office work.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLDeep, dark and noisy workplaces, Daylight autonomy
Less than 2% of England’s offset land has soldA year and a half into mandatory 10% Biodiversity Net Gain, 112 registered off-site projects promised over 4,000 hectares of habitat but under 2% of that registered land had actually been sold to developers by June 2025. On-site gains judged “non-significant” require no legal agreement and appear on no public register. The statutory habitat metric “has been demonstrated to be an ineffective proxy for wider biodiversity outcomes”, and developers favour fast, easy habitats — grassland — over woodland and wetland.External Open for expert reviewLeverhulme Centre for Nature Recovery, University of Oxford, 2025Habitat loss and cut ecological corridors, Biodiversity net gain
Lessons-learned list for lowering carbonPrefer renovation over new build and demolition; optimise usable floor area (four people in 150, 100 or 50 m²); design for resilience, adaptability and flexibility; design for disassembly and reuse; use renewable energy and minimise consumption; prefer materials with EPDs and natural/local materials; ensure the longest possible service life — with the caveat that building only from wood is not always the right answer.Expert Open for expert reviewLogistics Development in the concept of certification and LCAEmbodied carbon of new and demolished warehouses, Design for disassembly score, Space utilisation
Lifts and PVs eat a quarter of the carbon budgetElevators and photovoltaics — of which the building has comparatively little — together account for almost a quarter of total embodied carbon, and are where product-specific selection delivered the biggest gains.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusEmbodied carbon of new and demolished warehouses, High operational energy demand
Lighting is 65–95% of a dry warehouse’s energyIn non-refrigerated warehouses lighting dominates energy use, and LED retrofits cut lighting electricity costs by up to 70%.External Open for expert reviewSustainability Unboxed – Delivering on Logistics and Distribution WarehousesEnergy use intensity
Liquid cooling may quietly defuse the water fightAs IT density rises, air-based cooling becomes impractical and liquid cooling takes over; pushed to its conclusion that means a closed loop filled once at opening, so consumption falls. He presents the water controversy as partly a misunderstanding of a moving technology — while conceding it is still a real problem where traditional cooling persists.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsWaste heat and cooling of data centres, Water consumption, Robin Jesenský
Lizard habitat in a parking lotMany Czech warehouses install lizard habitats because they are cheap and easy — a pile of stones placed anywhere scores points. Whether such a habitat in the middle of a parking lot does anything for lizards is a separate, unasked question.Expert Open for expert reviewLogistics Development in the concept of certification and LCAHabitat loss and cut ecological corridors, Ecological connectivity
Location is king, and it moves with the marketA centre-of-gravity exercise: a warehouse serving all of Europe sits in mid-Germany; narrow the market to Germany alone and it shifts east; add Austria and Switzerland and it lands near the Cheb/Karlovy Vary border; add Eastern Europe and it sits squarely in West Bohemia. The dot map of Czech warehouse density is the physical residue of that calculation.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentMarek Nový
Location quotient as a design-relevant lensSector concentration in a city vs the national average (above 1 = specialised) shows European cities specialise in ICT, financial, professional and administrative services, while manufacturing and logistics are under-represented inside cities.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Logistics builds in a year; offices take four or fiveBecause logistics construction is so fast, the supply pipeline is only visible about 12 months out — beyond that, forecasting is “pretty tricky and actually probably meaningless.”Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Logistics centres cannot repack — so returns are destroyedE-commerce centres have no repackaging capacity: once a bag is opened the item cannot re-enter stock, so returns go to outlets or are destroyed. Some centres lack the resource even to inspect returns, and consumers exploit this by returning empty boxes. He suggests repacking, or a shop for returned goods, as possible programmes.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics Campus—
Logistics is a lens on the whole cityLogistics is a good lens for understanding the city as a whole, not only one building type.Expert Open for expert reviewPartner feedback – final review (2026)Closed sites that give little back to the city
Logistics is architecture built to disappearLogistics sits outside the city centre, tied to a highway, and is therefore not looked at; the brief reduces to cheap, fast, operational.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
Logistics is not one typology — it’s a carbon spectrumSome logistics buildings are completely dominated by embodied carbon because operational carbon is near-zero; at the other end, data centres have operational carbon that “completely eclipses” embodied. The designer’s first job is to identify which driver dominates before optimising anything.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses, Whole-life carbon
Logistics job vacancies doubled in five yearsThe European logistics job vacancy rate doubled to almost 3 % in five years; Czechia 5.6 %.External Open for expert reviewPrologis – Top Solutions to Source, Train and Retain Labour in Logistics Facilities (2019)Staff turnover and replacement cost
Logistics lives in the sprawl, not the cityTransport and storage is less concentrated in major cities than nationally; the activity forms rings of urban sprawl around cities rather than within them — including around Prague.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of propertyIlinca Maria Baciu
Logistics takes 2% of the land and 10% of the jobsFrance’s binding “zéro artificialisation nette” trajectory has become the sector’s central planning fight. The industry’s own defence: transport and warehousing accounted for just 2% of new land consumption in 2012–2021 while supplying nearly 10% of salaried employment, and 50% of new warehouses are already built on brownfield (friches). Their counter-warning: pushing sheds away from demand centres lengthens truck kilometres.External Open for expert reviewFrance Logistique, ZAN et logistique, 2025Land take of logistics buildings, Land take, Jobs created
Logistics warehouses are built for a five-year exitLogistics warehouses are typically developed as short-term investment products, with an exit or payback horizon of about five years.Expert Open for expert reviewPartner feedback – final review (2026)Designing for an unknown tenant
Logistics was GRESB’s lowest-scoring sectorIn the 2023 GRESB survey logistics participated less and scored lowest on average, with fewer certifications than office or retail.External Open for expert reviewSustainability Unboxed – Delivering on Logistics and Distribution WarehousesWhole-building energy data coverage
Long-hold warehouses cost 10–15% more to buildLong-hold or owner-occupier warehouses cost about 10–15 % more to build.Expert Open for expert reviewPartner feedback – final review (2026)—
Long-life loose-fit and design for disassemblyLongevity, adaptability and flexibility as a “long life loop”: these buildings arrive essentially as Lego, so the design question is how the elements are connected — no gluing, no welding, joints that can be undone.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Buildings that change slower than logistics, Design for disassembly score, Amy Naprstek
Low-carbon concrete has a scaling filterBest-case concrete could move from ~0.12 to perhaps 0.05–0.06 kgCO2/kg today, but many clever concrete chemistries cannot be built by real contractors and are therefore a waste of time. He maintains a “concrete technology tracker.”Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
Madrid’s 15,000-home annual gapFrom 2008 to 2024 Madrid completed on average around 20,600 homes a year while new household formation averaged just under 36,000. Copenhagen and Oslo show the same pattern; Helsinki is the counter-example, with completions outpacing household formation in 2017–2021 and house prices growing more slowly than the EU average.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Making it look fancy is not sustainable architectureTheir earlier office work is disowned as surface treatment. Sustainable practice, in their revised definition, means understanding how people move in a community and building space that survives the sector’s real cycle — a ~10-year lease after which fit-outs are ripped out and rebuilt.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
Mandatory site greenery as anti-landscape policyCzech industrial sites must keep 20–30% green, which he argues consumes ~30% more land than the same building would need in Germany or the US, pushes development onto open land outside the city, and produces greenery of no ecological value — including a demand to green a site that was formerly all concrete steel mill.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formLand take of logistics buildings, Habitat loss and cut ecological corridors, Green area ratio, Land take
Manufacturers and designers want opposite thingsEvery manufacturer prefers the simplest possible object, which has the highest chance of printing successfully, while architects want to express design freedom; the two expectations do not meet.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Manufacturing is a better neighbour than logisticsManufacturing generates fewer truck movements, better-paid jobs and longer tenure. Czech deal mix is unusual: more than half of last year’s Czech deals were manufacturing, against only 21% for Europe as a whole (3PL 43%, retail ~20% Europe-wide).Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentVisual impact of logistics on neighbours, Jobs created
Manufacturing knowledge upstream of formFor the World of Volvo, the glulam manufacturer (Wiehag, Austria) was engaged early so the design was informed by how the timber could actually be produced.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Manufacturing take-up more than doubledManufacturing was ~12% of European take-up in 2021 and has more than doubled its share by 2025, while retail and 3PL stayed flat. Presented as the best quantitative proxy for near-shoring actually happening.Expert DisputedPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Market windows open and closeOffice design in Prague is described as a window that opened around 2012, peaked in 2021 on startup money, and has now closed with investment drying up — positioning is as much timing as skill.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
Mass timber sites – tents, sealed containers, and a winter-open buildingWeather protection on timber sites is handled with a full tent over the works or by delivering sealed containerised prefab elements. Denmark’s largest timber building was left open through winter and still finished fine — the moisture panic is overstated.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Master plans must evolve or the investment leavesThe master plans need to evolve with this if they want to attract these investments.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
Materials that local trades already know how to repairTimber and straw are legible: anyone understands that wet hay gets pulled out and replaced, while a failed rubber gasket in an aluminium window produces a sense of alienation. He suggests that choosing materials could also mean considering the building trades a region knows, such as bricklaying.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics Campus—
Mayors get trucks, not taxesUnlike Germany, Czech municipalities capture very little tax or development contribution from industrial buildings, so local governments have almost no incentive to approve them.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentVisual impact of logistics on neighbours, Social acceptance
Measure it or you’re just claiming itCommitment to quantifiable nature-positive outcomes is what separates real ecological performance from a green facade as marketing.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureBiodiversity net gain
Melanopic light keeps winter workers awakeBeyond photopic lux, the vertical eye-plane melanopic value governs circadian response; in winter months, when natural exposure is low, untreated lighting leaves occupants sleepy, and artificial light has to be specified to compensate.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLDeep, dark and noisy workplaces
Micro data centres – who takes the wasteResponding to the mini-data-centres-next-to-houses idea (and a story about a man renting out part of his garden to a data centre company in exchange for free heat), he is open to the model but flags security control over critical infrastructure and end-of-life responsibility once the unit is obsolete after two or three years.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsWaste heat and cooling of data centres
Microclimate decides whether a masterplan worksWhether a comfortable microclimate can be delivered determines whether the neighbourhood is desirable at all.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient NeighborhoodsWind, heat and missing shade around large buildings
Minimal surfaces graded by force flowA published workflow fitted triply periodic minimal surfaces into a modelled load network for a bridge: the diamond variant performed best on overhangs, and the cell step size was scaled — denser where forces concentrate, coarser where they do not.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Minus 65% carbon on the structureThe first all-CLT Penny market in Czechia (2021/2022), at the time the largest CLT structure in the country, delivered a 65% reduction in the carbon footprint of the construction; three are built with five or six expected.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
Mission critical rewrites the brief”Mission critical” means the building itself is load-bearing for financial transactions, hospitals and even the power system, so it needs permanent on-site operation and maintenance. A warehouse of dry goods can survive a power cut; this cannot.Expert Open for expert reviewCloud in the city – data centres, urban development and implications—
Modularity as a design-process toolOnce you decide the building is modular, you can react to “make it longer, wider” during the years of design without changing the system.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’—
Morally obsolete before technically obsoleteBuildings may become obsolete morally before they fail technically; the offices being built now will likely need a facade refurbishment in 30–40 years purely to meet the moral criteria of a prime building.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Buildings that change slower than logistics
More glass does not mean more daylightKřečková opens on the persistent myth that daylight is solved by increasing the glazed proportion of the facade; in reality the thermal comfort penalty is severe, and daylight and overheating must be optimised as two simultaneous criteria.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLDeep, dark and noisy workplaces, Thermal comfort, Daylight autonomy
Most architecture is designed by nobodiesMost architecture that surrounds us is designed by people nobody knows.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
Most of them are already urbanThe majority of data centres sit in urban or suburban locations, or on city outskirts. The asset base is also hard to track because of confidentiality and because some announced projects are abandoned.Expert Open for expert reviewCloud in the city – data centres, urban development and implications—
Multi-storey manufacturing is a Czech tabooBuilding manufacturing in layers is “very new in Czech Republic”, because the default is one vast floor with no gaps or incisions so the process is unbothered by the outside. The client explicitly asked for the opposite.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Land take of logistics buildings
Multimodal siting – sea, rail, road, airBeyond proximity to northwest-European urban clusters, a small container terminal along the dyke brings goods in by boat, with highway, rail and an airport at Lelystad within reach. The inbound half of the building is markedly smaller than the outbound half as a result.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics Campus—
Municipalities get 3% — so they don’t want youCorporate income tax, personal income tax and social contributions all flow to the national level; the municipality’s only local income is property tax, roughly 3% of total public proceeds. German municipalities by contrast assemble land and pick the businesses that will fund them for 20–30 years.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
Mycelium pavilion that returns to the fieldFor Milan Design Week the studio grew mycelium components in a Politecnico lab next to the site and assembled them into a demountable scaffolding system: the scaffolding returns to a building site and the mycelium goes back onto the field.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased BuildingsEmbodied carbon of new and demolished warehouses, Design for disassembly score
Named toolchain, phase by phaseConceptual/competition work runs in Rhino + Grasshopper with Ladybug/Honeybee; transition to production runs through Rhino.Inside Revit; expert groups exist separately for the “Rhino universe” and the “integrated/Revit universe”.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Nature as the brief, not the garnish”Nature first” means every project begins by gathering ecological intelligence on soil, water, climate and biodiversity, and lets that sharpen the design strategy.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Nature branding became infrastructure policySingapore’s 1990s government adopted “city in the gardens” initially as a brand slogan, then converted it into an infrastructural regime, including legislation requiring greenery in every built project.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Nature designed to exclude peopleLarge areas were deliberately made inaccessible; limiting human pressure improves conditions for butterflies and insects, with a boardwalk and a few small access points.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusClosed sites that give little back to the city, Habitat loss and cut ecological corridors, Publicly accessible area
Nature is the last thing built, and the money runs outGood ecological ambitions are often a struggle in execution, because landscape is sequenced after the building and the budget is often exhausted by then.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Nature-based solutions because pipes can’t copeNature-based stormwater design is necessary: the volumes arriving in storm events now exceed what classical infrastructure can handle.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureStormwater and sealed surfaces on logistics sites
Netherlands has had carbon limits since 2018On the EU map of readiness, the leaders have had building carbon-footprint limits since 2022, the Netherlands since 2018, with databases and calculation tools already in place. Czechia is mid-pack: legislation and a new database, tools still in development.Expert Open for expert reviewLogistics Development in the concept of certification and LCAEmbodied carbon of new and demolished warehouses
New-build LEED never expiresLEED for new construction and interiors carries no expiry date; only LEED for Operation & Maintenance and WELL require recertification, on a three-year cycle.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELL—
Next – scraping Instagram to price placemakingA larger study is planned with the Technical University of Denmark, web-scraping unconventional sources including Instagram images, with economists converting results into valid metrics — able to answer, e.g., what dropping car speeds from 50 to 40 km/h does to placemaking value. She is explicit that no community engagement was involved yet.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
NIMBY survives the open dayAsked whether public visits soften opposition: people like visiting, “but you wouldn’t like this just to be built next door to your home.”Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Visual impact of logistics on neighbours, Social acceptance
No green premium in logistics yet, but it is comingAn investor reports no pricing premium or discount for logistics performance yet, slower than in other sectors, though one is expected.External Open for expert reviewSustainability Unboxed – Delivering on Logistics and Distribution WarehousesGreen rent premium, Green valuation premium
No IKEA parts fit a printed houseBecause every surface is curved and deformed, standard shelving, wardrobes and cladding are unusable; floors, ceilings, shelves and counters all had to be measured and made manually on site.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
No islands — connectivity is the metricBiodiversity work is not about creating isolated green patches; animals move to find food and habitat, so ecological corridors should link designed green to the surroundings.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureHabitat loss and cut ecological corridors, Ecological connectivity, Ece Yasar
No rule against confetti greeneryAsked whether LEED prevents green area being scattered into meaningless fragments (strips between parking bays) rather than kept continuous for biodiversity, the speaker could not point to a contiguity requirement — only a hunch that a half-square-metre patch would not be counted.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLHabitat loss and cut ecological corridors, Ecological connectivity
Nobody agrees how much water they useThere is no industry consensus on data centre water consumption; volumes are on the scale of a city’s use, and a lot of it is wasted. Water has become one of the most recent flashpoints, after years in which the argument was about power.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsWaste heat and cooling of data centres, Water consumption
Nobody asks about embodied carbon in CEETenants in Central and Eastern Europe have never raised embodied carbon with him; the certification push comes from developers chasing ratings and from UK/French investor pressure.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentEmbodied carbon of new and demolished warehouses
Nobody buys conceptual-stage LCAAsked whether they offer early-stage/parametric LCA: they did not, because no client wanted it. LCA contracts always arrive at detailed stage, driven by BREEAM requirements or financing.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
Nobody knows if twice the compute means half the floor areaHe has asked many people in the industry whether a doubling of chip performance halves the required square metres, and there is no answer. Buildings now being built may need half their area converted to something else in ten or fifteen years.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsBuildings that change slower than logistics, Adaptability
Noise – the logistics is the problem, not the buildingThe manufacturing process is mostly contained by the building; the loudest thing is the logistics. In a food factory the specific culprit is pumping flour and sugar from tankers into silos. Hierarchy of remedies: distance first, then soft materials and vegetation, then acoustic fences — and concentrate the noise in one place you can treat.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Visual impact of logistics on neighbours, Noise level, Distance to housing
Norms force oversized heat pumpsCzech norms compel designers to install heat-pump capacity the building demonstrably does not need. Blower-door and airtightness testing proves the lower demand, but unlike fire safety — where performance-based engineering is accepted in CZ — the energy norms will not accept evidence.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formHigh operational energy demand, Heating energy demand
Not having a strategy was the mistakeYears of working without a defined focus client or segment described as an outright error, recognised only recently. The reframing: stop pursuing a house style, start defining a segment.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
Not one forest offset achieved no net lossA global review of 32 studies across five countries — at least 300,000 hectares of offsets against 180,000 hectares of impacts, 48 policies or individual offsets — found only about a third reported achieving no net loss. Wetland offsets succeeded around half the time; of forest offsets, which are two-thirds of all offsetting worldwide, none demonstrated success. No avoided-loss offset was shown to achieve NNL.External Open for expert reviewzu Ermgassen et al., Conservation Letters, 2019Habitat loss and cut ecological corridors, Biodiversity net gain
Not recyclable, and the clock is always runningAsked directly whether the printed material is recyclable, the answer was no — which is why the research experiments were run in clay, which recycles easily. A collapse wastes several tons that must be shovelled, cured and disposed of, and additives such as small plastic fibres make it a mixed material; once mixed, roughly ten minutes remain before it sets inside hose, mixer and pump.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research labEmbodied carbon of new and demolished warehouses
Offsets have no place in building designHe rejects credits and offsetting at building level outright: unnecessary, confusing, and dangerous because it would become cheaper to buy your way out than to design well. He returns to Dieste — if you can buy your way out of a constraint, that building never gets invented.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and Delivery—
Old sheds are becoming unlettableEuropean logistics is bifurcating: over 80% of take-up in Italy and the UK is now in modern stock, over 80% of vacant space in the Netherlands is second-hand, and UK assets built before the 2000s have seen negative net absorption since the pandemic. Older stock struggles to meet modern requirements and “retrofitting is often impractical due to structural limitations.”External Open for expert reviewCBRE Investment Management, European Logistics – From Obsolescence to…Buildings that change slower than logistics, Embodied carbon of new and demolished warehouses
Old sheds knew things the new ones forgotThe older Kladno industrial buildings used natural/stack ventilation, daylight modulation and structural mass; today’s simplified shed geometry throws that passive potential away.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsHigh operational energy demand, Natural ventilation potential, Daylight autonomy
Omnichannel and 3PL, not online, are 60% of demandOmnichannel retailers, 3PLs and post/parcel operators together account for roughly 60% of take-up; traditional users take another 15–20%.Expert DisputedPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
One hour is the basic unit of an architectFrom roughly 25 to 65 is about 10,000 days and 80,000 hours. Putting a price on the hour gives an exact lifetime figure — but getting anyone to pay that price requires defining yourself as a problem solver rather than a designer.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
Only 20-year warranties, whatever the material20 years is what contractors will give, no different for timber than concrete. Cladding may need partial replacement after 20 years, but the frame, kept dry, can last indefinitely — like the 200–300-year-old timber-slab warehouses in central Copenhagen.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusEmbodied carbon of new and demolished warehouses
Only 20–25% built speculativelyOf roughly 2,000,000 m² developed in CZ, only about a fifth to a quarter went up without a signed occupier.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
Open Details – giving away the drawingsA Ramboll Foundation-funded research project publishes Henning Larsen’s 1:5 construction details, including biogenic-material assemblies, on a free platform for download and reuse — an explicit attempt to push low-carbon solutions out into the industry.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Operational carbon collapses, embodied carbon takes overBecause operational energy is falling so fast across the portfolio, the carbon locked into materials becomes the dominant term. The last decade was the energy decade; the next is the embodied carbon decade — across all typologies in the region.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsEmbodied carbon of new and demolished warehouses, Whole-life carbon, Operational carbon
Optimise a dream, don’t optimise a compromiseCost-first design lays “trip wires” across the process. Sell the ambition first, then spend the long tail of the project solving budget, fire and code against it.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics Campus—
Ornamental to performative — the key-species trickAsked how to move past decorative greenery: pick a key species (a bird, a larger mammal), build the storyline around it for client and community, and the species connected to it follow.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureHabitat loss and cut ecological corridors
Over-build the height, don’t charge for itWhen a tenant asks for 8 m clear height, Panattoni builds 10 m and absorbs the cost, because constraining height forecloses future uses.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formBuildings that change slower than logistics, Adaptability
Oversize the wires nowKnowing electricity demand for EVs will rise, you can strengthen the building’s electrical infrastructure and wiring at design stage to make the asset ready for the future.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That LastBuildings that change slower than logistics
Owner-occupier plus design-and-build explains the scoreČSOB SHQ reached 90 LEED v3 credits — sixth to eighth place in all of Europe — attributed primarily to two procurement facts: the investor was also the owner and end user, and it ran as a single design-and-build entity responsible for the whole process.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELL—
Owners don’t know where their own buildings arePortfolio clients operate at such a high level that they sometimes do not know where individual buildings sit; what they want is a portfolio-level risk picture and a decision on whether to invest in mitigation.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Ownership is the tenant’s defence against the landlord’s ratchetBuilt-to-own warehouses are invisible in the lease data everyone reports, yet would, he expects, correlate strongly with manufacturing: a tenant who invests heavily in automation cannot afford to be re-priced at renewal, so buys to control the real estate and the location.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
Parking hidden inside a fauna corridorExisting forest patches flanked the site with a gap the municipality’s master plan already intended to link. The project’s forest habitat wraps the car parks, simultaneously closing the fauna corridor and screening the least attractive part of the site.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusHabitat loss and cut ecological corridors, Visual impact of logistics on neighbours, Ecological connectivity
Pavement is the unsolved carbon problemFor logistics and industrial sites the dominant CO2 focus should be the pavement and external areas, not the building; asphalt has no real low-carbon alternative anywhere in the world, and the volume is enormous. Mycelium-bound paving with crushed-concrete aggregate is being trialled but cannot yet take heavy trucks.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased BuildingsEmbodied carbon of new and demolished warehouses, Large paved truck yards and waiting times, Embodied carbon intensity, Yard area per dock, Hynek Hrabík
Per-kilogram intensity is the wrong questionRanked as systems the story inverts: a concrete slab is high, steel-beam-and-slab still high, CLT the most efficient structural form. Intensity and usage must be read together.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
Permits are stretched, then sold emptyBecause the customer is unknown at permitting time, the strategy is to push height, access and traffic allowances to the maximum the zoning and community will accept.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formBuildings that change slower than logistics
Permitting runs on emotion, not dataThe stated mission with the in-house technical lead is “myth busting”: permitting and design decisions in CZ are emotion-based and unsupported by evidence.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
Permitting time is itself the developer’s productGetting a permit in CEE can take three to seven years (best case six months, worst four years for a Czech warehouse); once granted, it can add 20–50% to the land value. Developers run 10–20 person land-scouting teams and are paid only when a tenant moves in.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
Phasing over 20–50 years, while operatingThe phasing must be fixed at the very beginning because later options foreclose: phase one has to fund the final picture, “temporary” uses last 20 years, and each phase must be built while the rest of the site keeps running.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’—
PhDs embedded in the studio, not the universityDenmark’s industrial PhD model puts candidates on the company payroll with a university partner; Henning Larsen runs a stable of them on ecosystem services, biodiversity KPIs, additive manufacturing, transformation of existing stock, microclimate/future weather, acoustics and AI, plus 20–30 interns a year. One acoustics PhD produced facade prefab panels with acoustic absorption built in, and spun out a startup.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Pilsen – zero available sitesIn the country’s second-largest industrial market, a request for a 40,000 m² facility cannot be answered by a single site with a guaranteed move-in date inside two years.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
Placemaking is where the money is madeHardware produces an economic return, but hardware also produces a “place feeling”, which generates societal value — local shops, community, jobs — which loops back and raises the developer’s own return.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
Planar layers cluster stress to 250% utilisationForce-flow analysis showed the top layer’s weight spreads evenly through a non-planar sample, whereas planar layers form clusters with utilisation reaching about 250% — far beyond what the material can carry.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research labStructural utilisation
Planting the felled forest back doesn’t offsetAsked whether replanting trees taken from a site could be proven beneficial through LCA: offsetting is not accepted in official calculations, and even modelled as a scenario the sequestered carbon would be a very small number. The genuine benefits — biodiversity, green corridors — sit outside the carbon metric.Expert Open for expert reviewLogistics Development in the concept of certification and LCAHabitat loss and cut ecological corridors, Carbon sequestration by planting
Power and labour, not land, are the real constraintsThe historic constraints on logistics location have been power and labour rather than land; land is “normally surmountable.”Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Prague punches far above its weightPrague holds roughly 10–15% of the Czech population but accounts for 25–30% of the national economy, with ICT alone just under 20% of Prague’s GDP — a concentration credited for its office demand and productivity growth.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Prague’s pipes are an asset — sell the heatDistrict heating coverage is high in Northern and Eastern Europe and uncommon in Western and Southern Europe. Where a network already exists, the move is to pick plots near the pipes — or lay new pipe to reach them — recover the heat with a heat pump and sell it to the city’s district heating company, as is routine in Finland, Denmark and Sweden.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsWaste heat and cooling of data centres, Heat recovery radius, Waste heat recovery
Predicting simulations instead of running themHaving run large volumes of daylight and microclimate simulations, the team is training on that output to predict results rather than simulate each case.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Printed concrete weathers badly and must be sealedIt is porous, its layer cavities hold water and dust, and freeze-thaw can deteriorate it quickly; the practical response is wrapping during curing and then a hydrophobic paint or coating before shipping.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Printed shell as lost formworkBecause interlayer bonding undermines the printed object’s structural credibility, one workable strategy is to print a lost formwork and pour ordinary concrete inside, making the poured core load-bearing and the print merely the mould — which still removes conventional formwork. In Prvok, steel rebars were placed into small cavities and acted as columns.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Printing is mostly shovelling, not codingIn practice concrete printing failure means tons of set material to be hammered, shovelled into boxes and landfilled. Sectional test prints of the Prvok geometry almost always collapsed.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Production wants low, distribution wants high — for energy reasonsStandard warehouses are 12 m clear internally to suit racking; production tenants ask for only 6–8 m, partly because they don’t need high racking and partly because heating and cooling a tall volume is expensive.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentHigh operational energy demand, Heating energy demand
Property is infrastructure, not real estateWe don’t take our properties as really property, it’s infrastructure for business and it’s very important to look into it through this perspective.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
Rail freight has been stuck at 16.8% for yearsAgainst an EU policy target of a 30% freight modal share by 2030, rail’s share has stagnated at 16.8%. Every rail-served logistics scheme is being justified against a target the sector is nowhere near.External Open for expert reviewInternational Railway Journal, 2023Road freight impact
Rail is a rounding error – over 90% moves by truckMultimodal terminals exist but serve heavy automotive and heavy industry, not consumer goods. Companies request rail, then quickly abandon it because so few rail terminals have warehousing attached.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentRoad freight impact
Rain harvested to grow the wallsRoof rainwater irrigates the green façades and reduces load on the retention pools; the roof meadow itself absorbs water that would otherwise run off.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusStormwater and sealed surfaces on logistics sites, Water reuse share, Stormwater runoff reduction
Rainwater is not process waterUsing harvested rainwater in food machinery fails on purity: the debris requires an intense purification process. Wastewater heat recovery from the plant is suggested instead.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Water reuse share, Waste heat recovery
Ramboll’s benchmark database, and its warehouse gapRoughly 400–500 carbon assessments worldwide, with a public viewer called Compare. He admits the light-industrial/warehouse typology has comparatively few assessments in it, “because it’s not as common that we would do it.”Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon intensity
RCP 8.5 called the most reasonably dirty one8.5 it is like, let’s say business as usual, the most dirty one, let’s say the most reasonably dirty oneExpert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Read the metadata or you don’t know the numberThe most important discipline in using LCA data is reading the metadata behind the figure — representativeness, system boundaries, how the value was aggregated, which EPDs and manufacturers fed it. In One Click LCA the derivation of generic datasets is sometimes not findable at all.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
Recycled-PET envelope beats aluminium and concreteThe translucent panel system used (based on recycled PET/plastics) is presented as a better envelope option than aluminium, concrete or the alternatives.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Embodied carbon of new and demolished warehouses
Recycling can raise the carbon footprintReuse and recycling do not automatically reduce carbon. A thesis on recycled aggregate found the resulting concrete had a higher footprint than concrete from raw materials; a wall built from recycled concrete may need more concrete than one from primary material.Expert Open for expert reviewLogistics Development in the concept of certification and LCAEmbodied carbon of new and demolished warehouses, Material reuse share
Refinancing now comes with climate-risk questionsLenders ask more about environmental and flood risk at refinancing, so climate risk is now part of financial operations.External Open for expert reviewSustainability Unboxed – Delivering on Logistics and Distribution WarehousesDebt service coverage ratio
Reinforcement loses to nozzle collisionIdeally the robot would print a few layers and a rebar would be set upright into them, but the nozzle would then crash into the protruding steel on later passes — which is why printed structures cannot be properly reinforced and most projects post-tension after printing instead.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Removing a traffic lane raised apartment prices 20–30%Near Copenhagen’s meatpacking district a two-lane road was cut to one with a pedestrian/recreational strip in the middle, against loud objections from residents and shopkeepers. Resale values subsequently rose 20–30% and businesses moved in — a case for prototyping and temporary interventions as the way past the fear of loss.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Renewables as price insulation, not just carbonCities with high local renewable generation have pricing tied to domestic capacity and are less exposed to global oil and electricity spikes — making the Nordics and Spain competitive for AI investment.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of propertyElectricity price
Renovating an office saved about 80%A comparison of demolish-and-rebuild versus renovation for an administrative building showed savings of around 80% — but explicitly because the load-bearing structure, the most impactful material, was kept.Expert Open for expert reviewLogistics Development in the concept of certification and LCAEmbodied carbon of new and demolished warehouses, Embodied carbon saved by reuse, Thomas Olsen
Rents falling in CEE is good news, not badHeadline warehouse rents in CEE are roughly stable or slightly falling year-on-year, against Munich around EUR 7–11/m²/month and London around EUR 27/m²/month. He reads softening rent as an attractor of investment and jobs.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
Rents grew 70% nominal but only 15% real in 16 yearsPrime logistics rents hit unprecedented double-digit growth (15–16% at the 2022 peak) and are now at ~3.5%. But over 16 years nominal rents are up ~70% while real rents are up only ~15% — “not a terribly exciting performance in real terms.”Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Reshoring is not coming (contrarian)Asked directly whether deglobalisation and onshoring will drive European logistics demand, he says the data shows no such movement: European production and energy costs would outweigh tariff savings, and peripheral regions where manufacturing sits have weak demographics and cannot supply labour.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Residential and logistics cannot share a block; offices and retail canMixed use is rejected for housing on operational grounds — logistics runs 24/7 — but offices, retail and light industrial co-exist well; one Prague business park dedicates a third of its zone to retail, showrooms and a supermarket serving the surrounding community. The binding limit on industry inside cities remains road access.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formMixed-use ratio, Lindsay Daphne Macuja
Resilience is a second layer over sustainabilitySustainability assumes normal conditions; resilience asks whether the building survives the change in conditions and returns to normal operation. UCEEB is developing evaluation tools in an EU project: RB tool (resilient building) and RN tool (resilient neighbourhood), scoring hazard, exposure and vulnerability.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
Resilient assets, resilient returnsInvestors back green buildings when the return is visible; resilience is argued as return stability.External Open for expert reviewSustainability Unboxed – Delivering on Logistics and Distribution WarehousesCapitalisation rate, Net operating income
Restoration became law, and cities must not lose a treeThe EU Nature Restoration Regulation, in force since 18 August 2024, requires restoration of at least 20% of EU land and sea by 2030 and all ecosystems needing it by 2050, with member states bringing 30% of degraded habitats into good condition by 2030, 60% by 2040, 90% by 2050. It also mandates no net loss of national urban green space and urban tree canopy. Over 80% of European habitats are in poor condition.External Open for expert reviewEuropean Parliament, February 2024Habitat loss and cut ecological corridors, Tree count and canopy cover
Retail warehousing exists because master plans forbid mixing people and trucksConsumer access is not permitted on industrial plots, so a distinct “retail warehousing” subsector has emerged on highway junctions where zoning allows customers and private cars. The reasons are traffic and the safety hazard of mixing personal vehicles with trucks.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentPedestrian–truck conflicts on logistics sites, Closed sites that give little back to the city, Adam Večeřa, Julia Kopác
Retention ponds redesigned as habitatPlanning required retention capacity proportional to paved area. Rather than dry-then-full engineering basins, that mandated water volume was designed as wetland.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusStormwater and sealed surfaces on logistics sites, Habitat loss and cut ecological corridors, Stormwater retention volume
Rethink the logistics OF the cityReframing the lecture series’ own title: what changed in Copenhagen was the logistics of a city, not logistics as a building typology; the harbour front went from backside to front stage.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
Rethink the normalising unit per typologykgCO2/m² is the default but not always useful: carbon per patient for a hospital, per m² or per tonne of storage for a warehouse, per MWh or per MW of capacity for a data centre.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryCarbon per pallet handled, Carbon usage effectiveness
Rethinking the vehicle beats electrifying itThe Green Dash pilot (Latvia/Sweden, with Latvian Post and Riga City Council) did not electrify an existing van but redesigned the vehicle as a compact four-wheel electric cargo scooter, delivering a 30% efficiency gain versus traditional vans, reduced stop times and better working conditions. The same vehicle was tested by the city for street cleaning and park maintenance.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubsLast-mile delivery emissions and traffic
Retrofit pays now, new-build pays hypotheticallyEfficiency and renewables in existing sheds can pay back immediately for owner and tenant; in new-build the return appears only through rent, vacancy or cost of capital.External Open for expert reviewSustainability Unboxed – Delivering on Logistics and Distribution WarehousesGreen rent premium, Embodied carbon saved by reuse
Reuse can lose on whole-life carbonReusing an existing building saves upfront embodied carbon but often can’t reach modern operational performance; on a whole-life basis the reuse can come out higher. That flips again if the energy supply is renewable enough.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses, Embodied carbon saved by reuse, Whole-life carbon, Julia Godard Lombard, Katrin Rybinskiy
Risk analysis also finds the upsideRisk work is emotionally coded as negative, but the same analysis that shows one customer segment is no longer profitable may show that another has become viable. Transition risks are formally paired with transition opportunities.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Risk management is not a risk managerCompanies delegate risk to a risk-management team, often parked inside legal, and then consider the problem solved. Even the most capable team cannot manage risk for a whole company; escalation paths and cross-team communication are the actual mechanism.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Robot reach dictates architectural formThe industrial robot reaches roughly 3 metres with 6 axes, so Prvok’s printable pieces became C-shaped segments — the most convenient shape around a fixed robot — and nothing much larger can be printed. Segments were printed in České Budějovice and trucked to Prague on a steel base frame, with transport vibration and cracking designed for.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Robots don’t need a view — which makes the box more modularIn 20-plus years these buildings will be largely robotised; daylight may still be wanted, but windows to look out of will not be. Removing the window question makes the envelope far more modular.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Space, energy and labour needs changing with automation
Roof overhangs as anti-light-pollution deviceThe concrete roof overhangs at ČSOB SHQ were credited with eliminating light smog by preventing light emitted from the building escaping directly upward.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLVisual impact of logistics on neighbours
Rotate a 2D trick into a Gothic domeRotating the non-planar profiles around an axis and duplicating them five times produces a column-to-arch-to-dome structure, suggesting the method could deliver Gothic-like geometries rather than only extruded walls.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Same building, five consultants, five answersFinancing is currently tied more to operational performance, and embodied-carbon-linked finance will stay difficult while market variation is this wide.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon intensity
Same material, different path, opposite outcomeIn controlled tests with identical geometry, material quantity, layer count and print time, the only variable being planar versus non-planar toolpath, the planar samples failed while the non-planar ones held their shape. Changing only the print path buys both design freedom and structural soundness at no material cost.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research labStructural utilisation
Same rules for all materials, not subsidies for timberIn Germany and Austria there is effectively no price or standards difference between a concrete, steel or timber roof structure. The stated goal in working with the Czech standardisation agency is parity of rules across materials.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsEmbodied carbon of new and demolished warehouses
Scores converge, emphases don’tAcross the same administrative buildings the final scores from different systems come out broadly similar, but the systems weight different things: LEED looks more at people, BREEAM more at sustainability and energy.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
Self-generated power as a development advantageA developer holding a good location plus secured power — grid or self-generated — is in a materially stronger position; power has become another constraint on development for logistics.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performanceHigh operational energy demand
Sell the warehouse as a power stationFriedrich reframes the pitch to mayors: nearly every German warehouse now carries rooftop PV, and warehouses — data centres in particular — generate large volumes of waste heat that municipal heating plants can use. That is what has to be communicated.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsWaste heat and cooling of data centres, Waste heat recovery, Rooftop PV generation
Service trips – the invisible fifth of trafficService logistics — technicians, maintenance crews, repair vehicles — is routinely overlooked but can account for 20–30% of commercial vehicle traffic in cities, and demands flexible access and parking.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubs—
Seven-metre floors flatter the per-m² numberBecause floor-to-floor heights average ~7 m, per-square-metre carbon intensity is not comparable to an office typology. Normalised to office-like ~4 m floors, the same building would land around 4–4.5.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
Shared warehouses could cut construction by 60–70%Asked what unused potential exists, the answer is not a new building form but AI-and-app-enabled shared logistics centres — Penny and Nike in the same shed, packages routed to whichever slot is free. Estimated effect: a 60–70% drop in warehouse construction by using average existing space better.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itLand take of logistics buildings, Space utilisation
Ships are cheap, trucks are notRoad freight is extremely carbon intensive, while moving the same material by ship is “incredibly low carbon.”Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryRoad freight impact
Shrinking households multiply demandHousehold sizes are falling across European cities, so more dwellings are needed even where population growth is modest.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Silos are the recurring barrierSectoral silos between actors named as one of the most common barriers across urban mobility and beyond; EIT Urban Mobility’s match-and-connect function — 250+ partners, 1200+ organisations, 420+ pilots in 185+ cities — is explicitly built to break them.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubs—
Singapore’s 20 km road becomes a green corridorThe North-South Corridor converts a roughly 20-kilometre asphalt arterial — currently a barrier between neighbourhoods — into an integrated green corridor supporting biodiversity and community alongside traffic.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureEcological connectivity
Single-function land use is the real wasteOn whether large logistics hubs belong in city centres: the answer is not location but function-mixing. If a facility must sit outside the city, it must carry additional functions.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient NeighborhoodsLand take of logistics buildings, Mixed-use ratio
Single-picking is why e-commerce eats spaceE-commerce needs far more space per unit of sales because items are picked singly rather than shipped in bulk, returns need their own space (often a separate building), and SKU counts are an order of magnitude higher — a supermarket holds ~60,000 products, a DIY retailer ~70,000, an online retailer half a million or more.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performanceThroughput per site area
Site lighting at logistics scale is a biodiversity problemBecause the surfaces are so vast, applying standard street lighting to a logistics site produces light pollution at a scale that becomes a serious biodiversity problem.Expert Open for expert reviewLogistics Development in the concept of certification and LCAHabitat loss and cut ecological corridors
Six segments, one scarce resourceUrban logistics is multiple overlapping systems, all competing for the same limited space — which makes it a space-allocation and governance challenge, not merely a transport problem.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubs—
Six storeys of industry under 3,350 homesSEGRO V-Park Grand Union in Alperton, London, completed 2024, is the UK’s first multi-storey industrial development: 134,500 sq ft over six levels — two lower floors of loading bays and parking, four upper floors of industrial units — embedded in a mixed-use regeneration delivering 3,350 homes, 35% affordable, and up to 250 jobs.External Open for expert reviewSEGRO, April 2024Land take of logistics buildings
Skylights as a legislative contradictionCzech roofs carry large areas of skylights that he says are poor for building energy performance and for the processes inside — regulation pulling in opposite directions.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formHigh operational energy demand, Daylight autonomy
Skylights as wayfinding in a 565 m buildingAt 565 m long and 80 m wide, navigation is itself a design problem: a central “street” runs the length of the terminal with branch roads, and a rhythm of skylights gives occupants a sense of position deep in the interior.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusDeep, dark and noisy workplaces, Daylight autonomy
Slice resolution can be tuned locally, not globallyRather than lowering layer height across a whole object to resolve one window, layer height and orientation can be adjusted locally.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Soil is a biodiversity reservoir and a carbon bankMillions of species live in soil and it stores carbon, yet it is routinely removed during construction; she openly admits she doesn’t know how this is accounted for.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureHabitat loss and cut ecological corridors
Soil study at 2,500 hectares, not at the plot lineWith the Soil Science and Conservation Research Institute in Prague, Panattoni modelled roughly 2,500 hectares around the Kladno park — scenarios for how the buildings affect water behaviour and soil erosion, plus soil quality mapping. The finding he flags as striking: how poor the condition of Czech agricultural fields already is.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsStormwater and sealed surfaces on logistics sites
Solar is now a building code, not a choiceUnder the recast EPBD, all new non-residential buildings over 250 m² must have solar installed by 31 December 2026 where suitable and feasible; existing non-residential buildings over 500 m² must follow by 31 December 2027 when undergoing major renovation or permitted roof works. From 29 May 2026 every new building must be designed “solar-ready” — orientation, roof design and structural capacity to carry future panels.External Open for expert reviewEuropean Commission, Solar energy in buildings (EPBD)High operational energy demand, Structural utilisation, Rooftop PV generation
Spain’s housing crisis is six provincesThe much-protested Spanish affordability crisis is highly concentrated: roughly 6–7 provinces out of 50, all major urban cores. Spanish house prices rose about 10% in the last year against ~4% in the Eurozone, while “empty Spain” sees falling prices.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Speak their language or be invited too lateif you don’t start speaking their language, you will not be invited to the conversation. You will be invited too late.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
Speculative development sits at ~38%Normally 30–35% speculative versus committed pre-lets; currently ~38%, which he reads as a balanced market that has priced in the vacancy risk.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Stacking is normal — everywhere but hereMulti-storey warehousing has existed for decades in Japan, South Korea, Singapore and Hong Kong, where the largest facility rises to the height of a 22-storey building. Europe and the US barely build it: above three storeys a one-hour fire rating forces heavy steel or concrete, urban road layouts can’t take the lorry volumes, and rentable efficiency drops to about 75% once ramps, lifts and plant rooms are deducted. The first US ground-up multistorey — Prologis Georgetown Crossroads, Seattle, three levels, 590,000 sq ft — only opened in November 2018.External Open for expert reviewTransport IntelligenceLand take of logistics buildings, Space utilisation
Stakeholders don’t care what’s around the cityDecision-makers are dispersed global stakeholders whose interest is the profit of the area, not what the development does to its surroundings.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
Stop making objectsHer standing instruction to the architects in the studio.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Stored goods dictate where the building can goNetwork design starts from SKU characteristics — what the product is made of, how it’s packaged, how it’s stored — and material flammability feeds back into fire design and therefore into permissible location.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
Straightened rivers lost their capacity to floodYears of straightening rivers destroyed their flood capacity; returning natural meanders and space lets the river behave as a living system again.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
Straw façades cut truck movements fivefoldThe compressed-straw (Ecococon) façade elements are so light that, per square metre of façade, delivering them took roughly one fifth the truck trips precast concrete sandwich panels would have.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusEmbodied carbon of new and demolished warehouses
Structural stone – a knowledge problem, not a cost problemStone is near-zero-processing and returning as a structural material; France has built cost-effective limestone schools. Structural stone tolerates lower quality and coarser cutting than facade stone, and quarry spoil is cheap and structurally fine. Using stone can also delete the finishes layer entirely.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses
Supply chains gained layers, and buildings gained varietyThe old linear chain has fragmented into parallel models: cross-docks where trucks come in and vans go out, chains that skip the regional DC, direct-to-consumer from a single fulfilment centre. More models means more demand for space and a wider variety of building types.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Support strategies don’t scale down from plasticConcrete supports are heavy, stick hard and must be hammered off; thin plastic-style support columns would collapse under concrete, and 3D support structures would consume large amounts of material. Alternatives are lightweight filler balls or printing inside a large box of sand — but sand is heavy enough to deform overhangs under its own weight, and removed fillers leave material stuck to the top layer.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Sustainability arrives as a minimum, not an ambitionDevelopers install only the minimum EV charging needed to satisfy a BREEAM-type standard; more only if the tenant explicitly asks. He reports never being asked about electric or hydrogen trucks at all in CEE.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
Sustainability as risk eliminationWorking with Amazon taught the company that their “unique approach to sustainable operation” is inseparable from being risk-free.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
Switzerland is digging a 500 km freight tunnelCargo Sous Terrain proposes an automated underground freight network from Geneva to St Gallen at 40 m depth, CHF 30–35 billion, entirely privately funded, with enabling legislation in force since August 2022. First section, Härkingen–Zurich (70 km), targeted for 2031; a ZHAW study estimates the system with bundled delivery could cut daily truck mileage in Zurich by a quarter.External Open for expert reviewSWI swissinfo.chLast-mile delivery emissions and traffic, Road freight impact
Tailoring is a one-way doorBuildings can be tailor-made “to the point where it’s not usable for the future”, and with Amazon or H&M investing multiples of the building’s value in technology, the developer has no choice. Since the chance that another tenant uses such a building the same way after ~20 years is very limited, it must be possible to recycle it easily, ideally on site.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formBuildings that change slower than logistics, Design for disassembly score
Tech companies are buying BIM models with licencesSoftware vendors are approaching the studio offering free licences in exchange for its BIM models, because those models are training data for their industry.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Tell the story in the right orderThe skywalk was sequenced along the chronological axis of manufacturing — water, malt, then the process — so visitors do not start from the finished product. Two routes, public and guided, vertically stacked.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Closed sites that give little back to the city
Ten thousand options instead of oneFor the Fælledby neighbourhood, rather than developing a single scheme they generated and optimised across thousands of variants, tuning density upward while holding daylight stable.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased BuildingsDaylight autonomy
Tenant demand follows a Gaussian curveIndustrial tenants ramp production to only 20–30% in the first two years, peak at about five years, then decline; the building’s energy systems must be sized for the peak while running at 30–40% load in year one.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsHigh operational energy demand
Tested to 50 tons without failingPrvok’s printed structure was designed to norms for 5 tons from above (roof plus snow plus wind plus people on the roof, a scenario acknowledged as never happening). The test machine’s 50-ton maximum was reached with the structure still holding and the load-deflection graph still rising.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research labStructural utilisation
The asset class rotated three times in fifteen yearsLogistics was unfundable around 2008–09; COVID and long e-commerce leases made it the diversification target in 2021–23; today hotels lead, and logistics attracts capital only with long leases — with defence emerging as a key industrial driver.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
The barista must afford to live thereThe 15-minute neighbourhood is only honest if it covers workers as well as residents.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
The barrier is cultural, not technicalAsked for the biggest institutional obstacle to nature-core logistics, she names the capitalist system and design habit; European regulation, by contrast, has helped.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
The best logistics building he knows is a 1970s brick shedEladio Dieste’s warehouse in Montevideo: post-tensioned Gaussian brick vaults, a new roof on much older walls, still functional. It gets its strength from form, not mass. Dieste designed it that way because Uruguay had limited access to cement and steel — constraint forced the innovation.Expert DisputedNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses
The best-certified warehouse still looks like a boxTwo Czech examples — the highest-rated logistics building in the country and the largest logistics park near Pilsen — are shown next to a conventional warehouse; visually there is no difference.Expert Open for expert reviewLogistics Development in the concept of certification and LCAVisual impact of logistics on neighbours
The bigger the data centre, the bigger the targetConcentration is a security and resilience liability in a world with war in it, so a network of smaller facilities is systemically more robust than one or two giants.Expert Open for expert reviewCloud in the city – data centres, urban development and implications—
The biggest possible hall reflex is a carbon costLonger spans mean bigger beams; accepting shorter spans shrinks the structure. The level of flexibility built into a logistics building has to be balanced against it.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusEmbodied carbon of new and demolished warehouses, Buildings that change slower than logistics
The budget cut became the spatial ideaThe double-height, two-storey office with steel bridges came from omitting floor structure over part of the plan under a very tight budget; the saving on floor panels produced the volume and the visual connection.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
The budget is set before the architect arrivesArriving late means the budget was fixed in the previous phase, which removes the room for design entirely. Highlighting the problems from the beginning is what preserves design space.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
The build more taboo among young architectsA student-driven Danish activist movement argues Denmark already has the square metres it needs and refuses to work for offices that build new. When the studio finally won a Manhattan high-rise, nobody wanted to work on it.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased BuildingsEmbodied carbon of new and demolished warehouses
The building as a 3D mountainFor remote logistics she proposes treating the volume itself as biodiversity habitat, and argues that bringing nature closer to people is not optional.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient NeighborhoodsHabitat loss and cut ecological corridors
The campus behind your queryTwo named reference points for the new scale: the Sines Campus south of Lisbon (multi-building park, in development), and a recently opened AWS campus in the US that he told the students is the physical plant behind their own AI use.Expert Open for expert reviewCloud in the city – data centres, urban development and implications—
The carbon cost abatement curve — free interventions firstRamboll works out cost per kilogram of carbon saved. Early briefing interventions often save cost and carbon, so those come first.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses
The Cheese Boomerang replaces the Blue BananaThe classic Western European logistics corridor is being complemented by an emerging CEE corridor running Poland → Czech Republic → down to Romanian ports, which he calls the “Cheese Boomerang”. Power, rail and road investment is following that arc.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
The commonest mistake is saving carbon too lateTeams design as normal, then try to make it low carbon, which forces them to buy best-in-class materials — which is where cost enters. The right day-one question is not “how do we make our materials low carbon” but “how do we make this building low carbon.”Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses
The competitor is the gaming industryThe studio’s biggest future competitor is not another practice but the gaming and tech-adjacent industries, which can generate optimised outputs far faster — and logistics centres are named as exactly the typology where automated layout generation will land first.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
The computer took decades; so will thisOn the bubble question he refuses the sensationalist read: historically technologies like the computer took decades to seep into economies, so an immediate surge in either productivity or job losses is unlikely; AI’s clearer near-term effect is reinforcing the existing rich-north / poorer-south divergence in Europe.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
The crinkle-crankle wall saves bricksA serpentine garden wall exists to save material: a straight single-wythe wall collapses and needs two lines of bricks, while the zigzag stands with one. The same logic drove Prvok’s undulating wall surface — but it only works in two dimensions.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research labEmbodied carbon of new and demolished warehouses
The curb is contested infrastructureThe curb is the main interface between movement and access, and is now among the most valuable and most contested pieces of urban infrastructure, balancing deliveries, parking, pickups and public space.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubs—
The cycle store that came up out of the basementChallenging a brief moved bike storage from a concrete basement box to ground level; the client rebuilt the entry so you cycle into the building via a ramp past a cycle café. Planners loved it.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses
The Czech daylight standard has no ceilingThe national daylight factor metric tracks no maximum value, so over-glazing is invisible to the code: a room can be legally compliant while its workstations are unusable for screen work whenever the blinds are up.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLDeep, dark and noisy workplaces
The Czech Republic holds ~50% of regional stock — until Poland enters the frameCzechia has roughly 13 million m² of industrial floor space and takes up nearly half the region’s stock; Poland alone has 45 million m², roughly equal to all other CEE countries combined, which is why Poland is usually excluded from regional charts.Expert DisputedWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
The dearest credits eat sellable floorTwo families of expensive credits: artificial technologies with their control, regulation and measuring systems; and anything that consumes space inside the building, because that space cannot be sold or let and is full of technology.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELL—
The default logistics landscape is a lawnmowerThe standard treatment around logistics centres is large green lawns requiring constant mowing; the alternative is landscaping the same area so it becomes habitat.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusHabitat loss and cut ecological corridors
The design decision is made 2–3 years before anyone hears of itNetwork design and strategy takes two to three years before a tenant ever approaches the market. Total project timeline from board idea to operating warehouse is realistically four to seven years.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
The design outran the supply chainWorld of Volvo was conceived as a biogenic building that “outperformed” the manufacturing capability then available in Europe; it required an Austrian manufacturer and bespoke digital tools simply to describe the structure.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
The developer is not a philanthropist — that’s the planner’s jobAsked who ensures coherence when several developers assemble adjoining parks: developers maximise profit, and design quality across a precinct is the responsibility of the city architect, urban planner and government through the master plan.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
The developer is the interest-alignerNot the architect, not the contractor, not the capital. The function is to reconcile investor, bank, tenant, municipality and community interests — in his words “maybe not compromises”, but wins everywhere.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
The developer’s job is to push the supply chainThree parts: force new materials through the whole supply chain including small suppliers; engage clients and investors; and advocate for regulatory change — with German and Austrian colleagues lobbying alongside for Czech reform.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsEmbodied carbon of new and demolished warehouses
The digital Fort KnoxData centres as built are wide, industrial, gated, fenced and access-controlled, with prominent MEP, cooling towers and pipework on roof and flanks. He offers a personal verdict that they are architecturally poor.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsVisual impact of logistics on neighbours
The digital twin lies by 2–5 cmFresh material deforms as it prints, producing 2–5 cm of deviation barely visible to the eye but fatal to fabrication data: curves exported from Rhino for shelves and the kitchen counter did not fit, and the kitchen desk had to be remade to the as-built curvature measured on site.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
The dog-walker on the dyke as a design clientThe woman in Lelystad walking her dog should look at the building and read a generous gesture, not merely Bestseller’s profit.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusVisual impact of logistics on neighbours
The Dutch site was ecologically poor to start withThe reclaimed Dutch land was artificial, grid-like and near-monocultural — grass plus a hedge of essentially one tree species — so expectations were low; the ecological potential lay in the adjacent shore-water edge zone.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureHabitat loss and cut ecological corridors
The Dutch state architect said – fewer boxesThe Netherlands’ College van Rijksadviseurs issued a national advice on “(X)XL verdozing” with four words as its policy: minder, compacter, geconcentreerder, multifunctioneler — fewer, more compact, more concentrated, more multifunctional. It called for clustering zones, a ban on greenfield boxes outside them, “red-for-red” relocation of isolated sheds, and mandatory energy generation on roofs and facades. Dutch logistics floorspace grew by roughly 10 million m² in a decade, and seven provinces have since sought to restrain mega-DCs.External Open for expert reviewCollege van Rijksadviseurs, 2019Land take of logistics buildings
The early-decision curve applies to water and neighbours tooThe familiar carbon “decide early” graph generalises: the earliest design decisions govern energy, water and community impacts alike, and once built the building cannot be fixed.Expert Open for expert reviewCloud in the city – data centres, urban development and implications—
The ecotone is the design briefWhere forest meets beach there is a wetland belonging to neither, with higher biodiversity than either — so the zones where two, three or four urban systems collide are the highest-opportunity, highest-complexity design sites. Don’t tidy them up; keep the friction. A train station meeting a school should become a station-with-a-school.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
The electricity mix dominates everythingElectricity mix is the single largest determinant of the carbon footprint of everything, buildings included; the EU figure quoted is roughly 8% of total global emissions. Falling EU numbers come from renewables and nuclear, which is effectively carbon-free.Expert Open for expert reviewLogistics Development in the concept of certification and LCAHigh operational energy demand, Operational carbon
The employees are trapped outside the real worldThe major problem of the out-of-town logistics model is a human one: staff spend their working lives in a place deliberately located outside the city, cut off from what the speakers call the real world.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itDeep, dark and noisy workplaces
The energy price forecast is always wrongAsked to compute a heat-pump-versus-gas payback, his answer is that no defensible price curve exists: successive official forecasts of oil prices have all missed. The design response is not a better forecast but a solution robust across scenarios.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsElectricity price
The established digital hubs sit in flood zonesMapping physical climate exposure as a share of local GDP at NUTS-3 level shows several established data centre hubs are relatively exposed — Amsterdam to river and coastal flooding, London along the Thames — while the Nordics are less exposed, adding a resilience argument to their pull.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
The first taxonomy was too hard for materialsHe concedes the taxonomy is itself under pressure and being simplified: the first version was excessively demanding, especially on materials, while on energy it is clear, workable and well used by the market.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial Buildings—
The flood model was right, and the tenant kept tradingFlood risk analysis obtained from the insurer was modelled at concept stage; when the 2024 flood came, the roads around the Kojetín Amazon park went under water almost exactly as modelled, but the facility kept operating. One day of stopped production is a “terrible cost”.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsStormwater and sealed surfaces on logistics sites
The green wall on printed concrete diedGreenery placed against the printed wall was expected to spread over it but died quickly: in summer sun the concrete becomes extremely hot, killing even plants in pots with water. The irrigation pump also failed and nobody repaired it — maintenance being the big issue with living walls.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research labHabitat loss and cut ecological corridors, Green plot ratio
The hero-architect sketch is deadBecause performance requirements and ecological complexity now exceed any one discipline, the notion of the architect producing a brilliant sketch that becomes the project is obsolete; the team must include anthropologists, ecologists, traffic, light, climate and social-impact specialists.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
The junction paradox – less traffic, no capacityA brownfield redevelopment generating 500 cars where heavy industry once generated 2,000 can still fail its junction test, because through-traffic from newer developments elsewhere absorbed the capacity — leaving the developer to fund a new roundabout.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
The landscape architect arriving last is the old modelThe failure pattern named explicitly: architects make the building and the landscape architect is called just before completion to make it pretty.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with nature—
The largest rammed earth building in Europe is a warehouseHerzog & de Meuron’s Ricola Kräuterzentrum in Laufen (2014) is a 111 x 29 x 11 m herb storage and processing hall whose facade is prefabricated rammed earth made from loam, marl and material excavated on site, with tuff-lime mortar layers every eight courses to resist erosion, monolithic and self-supporting against an internal concrete frame.External Open for expert reviewHerzog & de Meuron, project 369Embodied carbon of new and demolished warehouses
The last node of the warehouse is a room in every buildingParcel boxes are already the final point of logistics and only growing; in future every building in the city will contain a room holding that last stage — distributed logistics as urban programme.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Last-mile delivery emissions and traffic
The lilac vs the oakLilacs are beautiful, familiar garden plants but non-native and support almost no insects; an oak supports roughly 250 living creatures. What sits “under the iceberg” of a design decision is what actually determines impact.Expert DisputedThe Henning Larsen Playbook for Biobased BuildingsHabitat loss and cut ecological corridors, Native species richness
The literal glass wall between collarsOffices look directly into the production hall. Acousticians measured noise at an existing Bestseller facility to specify that wall’s sound damping, plus vibration mock-ups for structure-borne noise.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusDeep, dark and noisy workplaces, Noise level
The market is back to its pre-pandemic lineTake-up rose ~6% in 2025 (13% year-on-year in H2) after the 2024 low, putting demand back in line with the pre-pandemic five-year average.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
The material bank argument to the clientThe commercial pitch for disassembly: the building may be worth a lot of money if you deconstruct rather than demolish it and sell off the excess material — the same beams could build sustainable housing.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Embodied carbon of new and demolished warehouses, Design for disassembly score
The MHE designed the building, not the architectAfter winning, the material-handling supplier’s design made the formally expressive competition scheme untenable. Expression was displaced to a few “special moments” — the pushed-in entrance, the roof restaurant bump, the office/production seam — likened to the nose of an aircraft varying a plain cylinder.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusSpace, energy and labour needs changing with automation
The middle-sized warehouse is disappearingCurrent Czech pipeline is barbelled: over 50% of enquiries are for ~1,000 m² cheap space in villages, and simultaneously 10–15 live requirements for 100,000 m²+ automated high-bay monsters. The former sweet spot of 20,000–30,000 m² has thinned out.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
The money is in logistics; the architecture isn’t — that’s the nicheWarehouses and logistics infrastructure are one of the largest segments of the building market, which means the budgets are there while architectural attention is not.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
The office is becoming the amenity that holds the workforceGood developers now build campuses with childcare, gyms and cafés, sharing services across multiple warehouses; a 10,000 m² warehouse typically carries 500–1,000 m² of office and showers. He claims these offices are becoming nicer than city offices.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentDeep, dark and noisy workplaces
The organic house shrank to two wallsThe original design was a free-form living-organism shape; after test prints it was reduced so only the two walls were 3D printed and the top room built in wood. Overhangs at the elliptical window had to be propped by foam layers stacked by hand.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
The plateau is why siting becomes the design leverBecause collective efficiency gains have stalled, the remaining opportunity is locational and systemic.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsWaste heat and cooling of data centres
The point is an interface, not a shedClosing takeaway: these buildings should not merely house machines and goods but create an interface between machine, people, city, urban fabric and site — succeeding when they become an ecosystem like a district, rather than an isolated utility in a virtual space.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’—
The power grievance is half rightCommunities argue that electricity going into a data centre is electricity not going into the energy transition or EVs; he accepts this as partly valid and partly not, rather than dismissing it.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsVisual impact of logistics on neighbours, Social acceptance
The printed material is not concreteWhat is printed is a cementitious mixture, far more expensive than ordinary concrete, that can solidify within minutes because of accelerant chemistry. The visibly darker top three or four layers are still wet; the greyish ones below have already started gaining strength.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
The production line length sets the buildingThe plan dimension is fixed by the length of the manufacturing line and the robot that runs it: it cannot easily be turned or rearranged. Two site options (north vs north-east loading) were tested against city connections; each had real downsides.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’—
The queue was four times the countryGreat Britain’s grid connection queue had swollen past 700 GW — around four times the capacity the country will need by 2030 — before NESO’s 2025 reform reordered it, protecting 283 GW of generation and storage plus 99 GW of transmission-connected demand. In the Netherlands the constraint is already binding: over 14,000 businesses were on the waiting list for a grid connection by October 2025, up from 12,000 months earlier, with the minister conceding “there are no easy solutions anymore.”External Open for expert reviewNESO, 2025High operational energy demand
The rating matters, not the certificateSale-premium data shows a 2010 LEED building sold at a 16% premium, while in Australia in 2011 a NABERS building scored −7.5%: the rules had moved from a 5-star to a 6-star scale, so buildings holding only three to four stars were penalised while five-star buildings still gained 3%.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELL—
The real energy breakthrough is building management dataAsked about technological breakthroughs, he names building management systems first: developers and landlords are getting good at collecting performance data and tuning buildings to time of day and season, with AI as the next step. A colleague adds that the missing half is knowledge about the people inside.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial DevelopmentHigh operational energy demand
The real green lever is 0.1–0.2 points of interestOne incentive that can move developers is financial: banks with deeper ESG policies can offer 0.1 to 0.2 better interest rate, which at these capital volumes is significant. Banks underwrite over 30–40 years, a longer horizon than the investor’s — which is why the alignment works.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
The reduction roadmap led to the activismThe reasoning came from the data in a Danish reduction roadmap: emissions cannot be reduced by building new, only by using what already exists.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased BuildingsEmbodied carbon of new and demolished warehouses, Embodied carbon saved by reuse
The region is treated as one product, not fifteen countriesEU membership, Schengen expansion and multi-country developer networks reduce friction, so a tenant can replicate an identical building from Czechia to Romania or Slovenia.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
The right answer is three materials, not oneOn a Copenhagen office, seventeen floor solutions were tested against weight, structural depth and carbon. Timber won on weight and carbon but lost on depth. The built answer used three systems in different zones.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
The risk model runs on ordinary architectural parametersThe inputs the diagnosis wants are the designer’s own variables: cooling system, energy consumption, heating type, the nearby surroundings and whether the building is attached to others, its shape, its façade colour, its window-to-wall ratio. An architect can fill the form “in a few minutes” because they already hold the data.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
The roof as employee groundRoof use need not be solar or green roof: on the factory they proposed a basketball court and a beehive. What limits a usable roof is worth asking rather than assuming.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Deep, dark and noisy workplaces
The same firm adopts AI differently in a cityThere is a consistent “urban premium” in AI usage, and part of it is a pure location effect: a law or consulting firm inside a city is more likely to use AI than the same kind of firm in a peripheral area, because urban firms compete globally. ICT shows almost no location effect.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
The sewage plant as the city’s best picnic spotA wastewater treatment facility in Aarhus was designed as an inhabited landscape rather than an excluded utility — landscape laid over the treatment works, turned into a learning space and public destination.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased BuildingsClosed sites that give little back to the city, Visual impact of logistics on neighbours
The shoebox is too crude for eye comfortParametric shoebox models are adequate for trading window area against thermal load, but not for eyesight comfort: they omit the window sill, wall thickness and window frame, and modelling at the fidelity glare analysis needs is too tedious to run parametrically.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLDeep, dark and noisy workplaces
The shop becomes a warehouse, the warehouse becomes a shopE-commerce proximity speeds delivery but weakens the shops that make a city centre feel alive. He speculates that the two could converge: the shop becoming logistics, or logistics becoming the shop.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusAdam Večeřa
The sky is brightening 10% a yearAnalysis of more than 50,000 citizen-science observations from 2011–2022 found night sky brightness increasing by 9.6% per year, nearly five times faster than satellites detect. A child born where 250 stars were visible will see about 100 by the time they turn 18.External Open for expert reviewKyba et al., Science, 2023, via NOIRLab—
The Spanish paradox – more workers, flat incomesSpanish cities with very strong population and employment growth have seen weak productivity and stagnating household incomes — headline growth masking a per-household standstill.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
The stranded gas station as a design briefAsked for a transition-risk example, they describe (deliberately unnamed) an operator of numerous filling stations who knows electrification will remove demand for gasoline, and is now redesigning the asset’s revenue model: EV charging plus something to entertain people during the charging wait.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That LastBuildings that change slower than logistics
The UK model – pay, and they must deliverIn the UK a residential zone triggers a costed list of schools, bus stops and rail connections funded by a developer contribution, and the municipality is legally obliged to deliver or refund. In CZ the developer pays a contribution the city spends elsewhere — and still builds its own infrastructure.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—
The whole point is being in business in 20 yearsTo ensure that they are still in business in five, ten, twenty years and not just surviving but thriving.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
They don’t forecast AI at allOxford Economics does not formally forecast AI growth because of data reliability. Instead they proxy it: sector mix, workforce education levels, willingness to return to education as an upskilling proxy, and R&D/investment flows by city.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
They tested it on their own office and found flood riskThe demonstration building is EY’s own Prague office; the diagnosis returns heat, rainfall and floods as its main climate risks, though existing adaptation measures pull the vulnerability score below the exposure score.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Thirty-metre freezers are a heat sourceIn the food factory the 30 m freezers and chillers produce so much excess heat that it can heat the parts of the building where people are concentrated. “Once you do things like this, it’s no brainer” — what you need is interconnectivity.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Waste heat recovery
Thixotropy, and why you hammer the hoseThe mix behaves opposite to ordinary intuition: agitated it flows like honey, at rest it stands solid, which is exactly what lets a fresh layer hold its shape before the chemical reaction starts. It is also why crews hammer the hose — added vibration re-liquefies material that has stiffened during a pause of as little as five minutes.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Three failure families, one weakest linkPrvok exposed three groups of problems: the containment/stair-stepping mismatch between sliced object and digital model, early-age deformation and collapse, and anisotropy — strong within a layer, weak between layers, so cracks occur at layer interfaces.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Three price scenarios, not one numberAsked how to plan under energy price uncertainty: a low-risk baseline, a middle case, and a high-risk case — three price and conversion scenarios.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsElectricity price
Three tiers of ambition on a plotAn implicit ladder: the default is bulldoze and build; better is to avoid net loss (keep the trees); best is a measured biodiversity net gain.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureHabitat loss and cut ecological corridors, Biodiversity net gain
Three years and 3,000 people, not a drawing boardAgainst the normal masterplanning method, Downsview took three years of work with over 3,000 residents to “massage” the winning competition proposal into something robust.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
Timber buildings overheat without thermal massLosing concrete’s night-cooled thermal mass means timber buildings show overheating; designers must be far more careful about glazing ratios.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased BuildingsEmbodied carbon of new and demolished warehouses, Thermal comfort
Timber is scarce — spend it displacing steel and concreteTimber’s value is displacement, not maximisation. There is not enough of it today to displace those materials at scale, so it should be used sparingly and precisely.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses
Timber sells on schedule, not on carbonThe business case is time and money: price roughly the same as the standard build, one month saved, so revenue from the client’s core business starts earlier; simple repeatable shapes remove costly detailing; mistakes are cheaper to fix.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itEmbodied carbon of new and demolished warehouses, Construction cost
Timber turns 60,000 t CO2 into a surplus — conditionallyViewed “in carbon goggles”, the conventional version of the timber district would embody almost 60,000 tonnes of CO2; in timber it shows a surplus of carbon sequestration — explicitly conditional on the timber not being burned after 50 years, with EU legislation expected to support that accounting.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient NeighborhoodsEmbodied carbon of new and demolished warehouses, Embodied carbon intensity, Life-cycle impact by stage
Timber, brick and light concrete came out near-identicalOne house designed in three material variants (Porotherm, autoclaved light concrete, timber) showed only very small differences in total emissions, because the foundations dominated. The timber structure itself was lower-impact, but that advantage disappeared in the total.Expert Open for expert reviewLogistics Development in the concept of certification and LCAEmbodied carbon of new and demolished warehouses, Embodied carbon intensity
Today’s sheds are tomorrow’s convertible stockThe generic modern box — 10–12 m clear height, good column grid, flat floors — is the frame that converted well in Western Europe, and is expected to absorb data centres quickly. City-swallowed older industrial in Prague is already becoming fitness centres, basketball courts and retail parks.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just formBuildings that change slower than logistics, Embodied carbon of new and demolished warehouses, Adaptability
Today’s waste stream should be tomorrow’s solved problemBuilding with a waste stream (such as fibreboard from construction) should be temporary: if the waste problem is solved, in five years the recycled material should come from a different stream.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics Campus—
Toolchain as hiring criterionHenning Larsen will not employ architects who work in SketchUp; Rhino/Grasshopper is mandatory because the tool is the shared language across a global studio.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
Topology optimisation isn’t buildable yet — use waffles meanwhileOn 3D-printed and topologically optimised slabs (Block Research Group name-checked), the lab-to-site gap is real. Intermediate steps are waffle slabs, cast void-forming, then more sophisticated tessellated precast.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses
Traffic engineers are expert space-consumersGreen corridors are a fight over surface area: since no new space exists in cities, corridors mean reducing paved surface and increasing permeable softscape, which simultaneously solves rainwater.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureStormwater and sealed surfaces on logistics sites, Impervious surface ratio
Translucent roofs trade lighting carbon for heatRoof lights cut lighting energy and possibly embodied carbon but raise indoor heat in hot climates, so the metrics must be weighed together.External Open for expert reviewSustainability Unboxed – Delivering on Logistics and Distribution WarehousesDaylight autonomy, Thermal comfort, Embodied carbon intensity
Transparency – 600 PDF pages versus an open toolDGNB’s methodology is public but arrives as roughly 600 pages of PDF; BREEAM’s checklist is findable with effort; LEED’s is essentially gated behind registration. SBTool CZ is free and online, has run for 15 years, and adds a generic typology by end of this year.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
Transport is half the supply-chain cost, rent a tenthFor a standard ambient distribution warehouse, roughly 50% of supply-chain cost is transport, 20–30% labour, and only 5–10% rent. This inverts the usual real-estate framing.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
Tuning a building takes two yearsGetting a finished building into a genuinely efficient operating state can take two years, and it is always mediated by the people and the company that occupy it. Commissioning is not an event.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLHigh operational energy demand
Twelve months from signature to handoverSite, general contractor and basic concept are all ready before the client is signed, but the entire construction must be delivered within 12 months — and the concept still has to be reworked in the first few months around a client technology the client itself cannot yet specify.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial Buildings—
Two Czech databases disagree by 10%+Comparing One Click LCA’s data against the Czech data.LCA.cz database gives differences of 10% and more — even using the datasets One Click LCA itself labels as representative for Czechia. Using Danish data, with its very green energy mix, produces completely different numbers and limits.Expert Open for expert reviewLogistics Development in the concept of certification and LCAEmbodied carbon intensity
Two engines, or growth goes wrongPopulation growth and productivity growth solve different problems and must run together; with only population you get congestion and stagnating household incomes, with only productivity you get an efficient, ageing, slow-growing city.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Two fewer sick days pays for the buildingCiting certified-building data, workers are typically sick two days less per year in certified buildings; those two days of inactivity per employee are what actually makes the business case, not kilowatt-hours.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLDeep, dark and noisy workplaces, Worker well-being
Two knobs decide everything – scenario and horizonEvery climate risk result is a function of exactly two choices — which IPCC scenario and which time horizon. RCP is explained as watts per square metre of additional forcing; RCP 8.5 is stated as 8.5 W/m² with a warming range around 3.2–5.4°C.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Two pilots contradict each other on batteriesBattery swapping and on-street static charging are presented as competing answers to the same question, with swapping carrying its own operational cost and extra service-vehicle trips; the on-street charging pilot in Norway, Finland and Sweden showed a 50–70% reduction in battery swapping and fewer service trips.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubs—
Two specified layers failed on siteThe interior clay board proved too fragile and not humidity-resistant during installation and was swapped for plaster board; the wood-fibre wind stopper was replaced with a Class A non-combustible weather board to give a fire separation between rain screen and straw element.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics Campus—
Two storeys because there was no third siteSEGRO and IKEA’s Paris Air² Logistique at the Port of Gennevilliers is 63,000 m² over two storeys, built vertically because it occupied the last large plot available in the port. BREEAM Excellent, river-rail-road connected, serving Parisian stores.External Open for expert reviewSEGRO, 2019Land take of logistics buildings
Two thirds of energy is lost as heatAbout two thirds of all energy in current US and European systems is lost as heat, so electrifying raises end efficiency — the reason heat pumps and PV win.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial Buildings—
Two twin harbours, opposite performanceNorth Harbour (Århusgade) and South Harbour (Sluseholmen) are near-identical in location, size, age and typology, yet the higher placemaking score tracks higher average price per m², lower reported loneliness, and far more visitors in the flow data.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient NeighborhoodsSocial interaction index
Under triple-net, the savings walk out with the tenantOwners decide on construction but tenants pay utilities, so efficiency investments rarely return to the owner directly.External Open for expert reviewSustainability Unboxed – Delivering on Logistics and Distribution WarehousesOperating expense ratio
Under-construction volumes down ~40% from peakSpace under construction has fallen roughly 40% from the 2022 peak, with declines in Italy, Netherlands, France, UK and Germany. Completions fell ~7% in 2025 to roughly 15–16 million m².Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Unknown tenants make speculative warehouses oversizedSpeculative warehouses are oversized because the tenant, its needs and the lease length are unknown at design stage.Expert Open for expert reviewPartner feedback – final review (2026)Designing for an unknown tenant, Oversizing ratio
Utah’s random giants are not the modelPrefacing that this is a personal view and not his company’s: AI-serving data centres can be sited anywhere, and in the US go wherever land is cheap and building is easy — producing very large projects in “completely random” places. He is “really not a big fan” of that model.Expert Open for expert reviewCloud in the city – data centres, urban development and implications—
Vacancy – 5.5% average, but zero in Munich and HamburgEuropean logistics vacancy averages ~5.5%. Slovakia, Poland and Spain run high; the UK jumped from 2.5% to 7%; Germany stays very low, and Munich and Hamburg have “literally no vacancy,” which drives their rental growth.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
Vertical zoning is the answer to people-meet-machinesWhere public and logistics collide, stack them: the ground floor is strictly logistics and industry, and the public route runs above on an elevated skywalk. Safety first, without compromising logistics efficiency.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Pedestrian–truck conflicts on logistics sites, Pedestrian–vehicle conflict points, Khrystyna Verbitska
Volvo’s roof belongs to everyoneIn Sweden, allemansrätten (right to roam) means nature cannot be owned: the World of Volvo site is Volvo’s, but no ticket is required to walk the roof and surrounding landscape.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased BuildingsClosed sites that give little back to the city
Warehouse belts create heat islands between fieldsLogistics clusters form large heat islands, and because they sit among agricultural fields, the heat island compounds drought problems in the surrounding landscape.Expert Open for expert reviewLogistics Development in the concept of certification and LCAWind, heat and missing shade around large buildings, Urban heat island effect
Warehouse demand weak; data centres and defence carry itFor Prague and CEE he expects weak near-term industrial and warehousing demand, with German weakness spilling over. The offsetting drivers: data-centre construction and servicing logistics, and — more speculatively — Germany’s planned fiscal and defence spending creating demand for defence facilities and related warehousing.Expert Open for expert reviewThe Geography of Growth – Cities, AI, and the future of property—
Warehouses aren’t sexy — but that’s changingHe opens by conceding architects’ likely prejudice, then counters with multi-storey warehouses in Hamburg and GLP’s sky-blending facades.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performanceVisual impact of logistics on neighbours
Warehouses break the user-comfort premiseCertification tools are still built around a human user. In a highly automated hall with robots and almost nobody inside, user-comfort criteria have no subject — named as a fundamental limitation for this typology.Expert Open for expert reviewLogistics Development in the concept of certification and LCASpace, energy and labour needs changing with automation
Warming has social consequences that are also risksSSPs are introduced as the second scenario family, on the argument that a warmer environment produces socio-economic consequences — migration, higher rates of illness — which a complete asset-level assessment has to cover.Expert Open for expert reviewBeyond the Concrete – Designing Buildings That Last—
Waste heat is already an approval conditionIn parts of Europe, particularly the north, heat recovery into district heating is now a routine design and planning consideration every time a data centre is submitted for approval — homes, offices, swimming pools.Expert Open for expert reviewCloud in the city – data centres, urban development and implicationsWaste heat and cooling of data centres, Waste heat recovery
Waste is the segment cities actually controlUnlike other segments, waste flows are predictable and publicly controlled, which makes them a strong entry point for electrification, data-driven optimisation and system-wide innovation — and ties directly to urban design decisions such as bin placement, access and street layout.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubs—
We assign a moral price to materialsThe barrier to reuse is perceptual as much as technical: we look at old artwork and old construction elements with awe, but dismiss recently reclaimed material. “The older it is, the higher the value in our perception” — while young reuse material is dismissed. In the Netherlands, reclaimed piles are considered higher aesthetic quality than new ones.Expert Open for expert reviewChallenge the perception of industrial architecture as ‘boxing’Embodied carbon of new and demolished warehouses
We can price carbon, not natureThe profession has become good at calculating carbon and can now calculate biodiversity net gain, but has no way to value air cleaning, stormwater handling or community wellbeing — so nature has no monetary standing in the argument.Expert Open for expert reviewNature positive by design – Creating lasting impact by designing for and with natureSocial cost of carbon
We had no criteria, so we borrowed Gehl’sTo score placemaking they had to adopt Jan Gehl’s 12 criteria, because no other benchmark existed in academia or anywhere else.Expert Open for expert reviewFrom Plot to Place – Designing Thriving and Resilient Neighborhoods—
We killed our own business thereAfter seven years with Penny, YUAR produced a design manual allowing the chain to replicate the store nationally without them. Roughly 80% of the documentation can be identical, but the authorisation of each permit must still be unique — which is the residual fee.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
We planned people for decades; goods got none of itWe spent decades planning how people move. And now we really need to plan how goods are moving around our cities with the same level of attention.Expert Open for expert reviewIntegrated Urban Logistics – From last-mile to mobility hubs—
Weights should change with typologyIn SBTool CZ the weighting differs per building type: for administrative buildings energy, drinking water and LCA dominate; for schools the heaviest criteria are indoor environmental quality and interiors.Expert Open for expert reviewLogistics Development in the concept of certification and LCA—
WELL is the one that waitsLEED and BREEAM are assessed through design and construction and effectively close at commissioning; WELL is aimed at the operational state, at how the building affects its occupants once running.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELL—
Wetlands chosen partly as carbon sinksAnalysis showed wetlands sequester the most carbon of any landscape type, making the retention wetland a carbon strategy as well as a stormwater and biodiversity one.Expert Open for expert reviewBig Box, Small Footprint – Lessons from Bestseller’s Low-Carbon Logistics CampusCarbon sequestration by planting
What is sold as 3D printing is 2.5DThe promise that printing lets you build anything is not met: most projects draw a plan and extrude it upward, with no overhangs or openings — stacking identical layers, properly called 2.5D printing.Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
What performs is what you can’t seeThe photogenic surface versus the invisible performance: acoustics solved selectively (enclosed meeting rooms, plus porous unchipped brick left raw because it absorbs more sound than a flat wall), and above all layout and exposure.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itDeep, dark and noisy workplaces
What will we do if we replace every job by a robotLeft open as a social question, after noting that a facility went fully automated because human error had cost the company large sums.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itSpace, energy and labour needs changing with automation, Jobs created
White facades, urban heat and the wind that saves themUncertain about reflection and urban heat risk from their standard white facade, the team ran microclimate simulations with external experts; wind, building orientation and surrounding greenery together proved sufficient to manage the heat and glare risk.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsWind, heat and missing shade around large buildings, Urban heat island effect
Whole-life carbon usually isn’t wholeLifecycle modules follow EN 15978 (A upfront, B in use, C end of life, D beyond). C is typically under 10%; A is typically one third to 50%. People routinely say “whole life carbon” while silently excluding modules, and national regulations differ on which.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryLife-cycle impact by stage, Whole-life carbon
Why CEE – demand, workers, cost — in that orderA 2025 KPMG survey of ~130 companies found local consumer demand the top reason for choosing CEE, followed by availability of qualified workers, then low labour cost; 22% of German respondents cited ease of doing business. He notes the region’s rare “sweet spot” of university-educated technical staff alongside a deep blue-collar workforce.Expert Open for expert reviewWhy CEE is the Hottest Location in Europe for supply chain, logistics and industrial Development—
Wind in Czechia is a mentality problemPressed on why wind generation next to a warehouse is normal in the Netherlands and effectively impossible in Czechia, he declines to blame regulation alone: master planning matters, but so does the mentality of the region — the same pattern he sees in slow EV uptake.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial Buildings—
Wire reinforcement doesn’t bond like rebarGroups in the Netherlands deposit steel wire directly into the layers, but a smooth wire embedded in this mixture, without proper compaction around it, does not bond as well as reinforcement in conventional concrete — where steel and concrete must “become very good friends.”Expert Open for expert reviewPrinting Against Gravity – From the construction site to the research lab—
Workplace investment helps keep warehouse staffWorkplace investment helps attract and retain warehouse employees.External Open for expert reviewSavills – What Warehouse Workers Want (2020)Deep, dark and noisy workplaces, Worker well-being
Yields – 8% then 3.5% then 5%, now flatLogistics yields fell from ~8% in 2009–10 to a low of ~3.5%, corrected sharply during the rate rises to ~5%, and have levelled at about 5.25% — roughly in line with retail, while office yields have begun compressing again.Expert Open for expert reviewPerforming Despite the Headwinds – Understanding the drivers of European logistics performance—
You can buy a second-hand warehouseA UK website sells used buildings; because logistics buildings are highly standardised, buying one — or several — and recombining them behind a new facade would save a massive amount of carbon.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and DeliveryEmbodied carbon of new and demolished warehouses, Buildings that change slower than logistics, Embodied carbon saved by reuse
You can have a dog, but not a catBuying an apartment at Fælledby means signing up to keep only indoor cats, because free-roaming cats predate the small birds the biodiversity strategy is built around. Nature accessible to everyone, owned by no one.Expert Open for expert reviewThe Henning Larsen Playbook for Biobased Buildings—
You can model anything; the client is the unknownModelling capability is not the constraint — understanding how the occupier behaves inside the building is. Panattoni calibrates models using operating data from a comparable building the same client runs in another country.Expert Open for expert reviewFrom Model to Reality – Sustainability in Industrial BuildingsHigh operational energy demand
You can’t reinvent the warehouse any more than the containerWarehouse form is treated as effectively settled, for the same reason container dimensions are: it is standardised to a worldwide system. Innovation therefore has to happen in operation and sharing, not in shape.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for it—
Young architects engaging with logistics is valuableIt is valuable that a young generation of architects engages with logistics.Expert Open for expert reviewPartner feedback – final review (2026)—
Your professional emissions dwarf your personal onesPersonal footprints in the UK/EU run about 5–8 tonnes per year; the emissions a designer influences professionally are enormous by comparison, and architects have the largest influence of all.Expert Open for expert reviewNet Zero That Holds Up – Whole-Life Carbon, Design Choices, and Delivery—
Your site decides a whole credit blockTransport credits depend on the site: with no metro, tram or bus you cannot earn a single point, and with no cycle route passing the site you cannot claim bicycle facilities however good the internal provision. The fallback is earning at least one credit for green vehicles.Expert Open for expert reviewCriteria for a Green Building – Beyond energy performance LEED - BREEAM - WELLPublic transport accessibility
Zero incentive for greenery in logisticsAsked directly how strong the incentive is for developers to add trees and green space to Czech logistics parks, the answer is flatly negative for logistics — while the same incentive is growing for offices, because offices must now compete to pull people back in.Expert Open for expert reviewBuild Your Own Playground – Architecture where no one looks for itHabitat loss and cut ecological corridors
Zoning permits you to apply, not to buildA Czech master plan grants no timing certainty and no infrastructure capacity. Developers must buy and permit land years before any customer exists: up to 10 years in Prague, 1.5–5 years in regional towns.Expert Open for expert reviewIndustrial Architecture as Living Infrastructure – Why future design is defined by systems, data, and adaptability, not just form—