ČSOB SHQ reached 90 LEED v3 credits — sixth to eighth place in all of Europe — attributed primarily to two procurement facts: the investor was also the owner and end user, and it ran as a single design-and-build entity responsible for the whole process.
— Paraphrased from the lecture
| Where in the source | ~00:34–00:35 — anchor: “the investor is owner as well” |
| Confidence | high |
Context
Petr Zahradník (EkoWATT) explains why the ČSOB South Headquarters in Prague, his main case study, reached such a high LEED v3 score, pointing to how the project was procured. The European ranking reads ‘6:00 to 8:00 position’ in the transcript.
From the transcript
So 90 credits in [LEED] version 3 equals to [6th to 8th] position in entire Europe. So there are not many projects that are in similar overall quality than is this one. […] When we look at the process, actually why the [building] is that good: first, and actually the main reason probably, is that the investor is owner as well. So it’s not a typical development when 1 entity builds a building and then it sells, then the building is sold to anyone else. […] Another important thing is that the project has been prepared as a design and build project. […] during the whole process, there’s one entity that is responsible for the process and for continuous updates and upgrades of the design. And actually it helps identify potential efficient measures, I would say, in time.
Automatic transcript, presentation, 00:33:50. Lightly cleaned: repeated words and fillers removed, omissions marked […], editorial insertions in [brackets].
Connections