Getting a permit in CEE can take three to seven years (best case six months, worst four years for a Czech warehouse); once granted, it can add 20–50% to the land value. Developers run 10–20 person land-scouting teams and are paid only when a tenant moves in.
— Paraphrased from the lecture
| Where in the source | late Q&A — anchor: “their job is to just do the permitting” |
| Confidence | high |
Context
James Fitzgerald (IO Partners) gives the permit time for a new Czech warehouse when walking through a project timeline in the presentation. In the Q&A, asked how such deals work, he describes how logistics developers make their money.
From the transcript
If it’s not existing and they need to build a warehouse that could take in the Czech Republic anywhere from[…] in a good scenario, six months to three or four years to get a permit […] — (Q&A) So the way the way deals work is generally developers […] their job is to just do the permitting. They come along and they buy, they […] look at industrial zones on master plans. They have full teams, yeah, like 10[,] 15[,] 20 people in their teams just scouting for land. […] getting a permit in Central and Eastern Europe can take three to seven years and there’s value in that once you get a permit. […] once if it’s zoned industrial and it’s worth certain money, once you get a permit, it can add anywhere from 20 to 50% of the land costs on top. […] So they buy the plot, get the permit, try to find the tenant, build the warehouse, and they only get paid once the tenant moves in.
Automatic transcript, presentation, 00:49:16, and Q&A, 01:37:06. Lightly cleaned: repeated words and fillers removed, omissions marked […], editorial insertions in [brackets].