Because interlayer bonding undermines the printed object’s structural credibility, one workable strategy is to print a lost formwork and pour ordinary concrete inside, making the poured core load-bearing and the print merely the mould — which still removes conventional formwork. In Prvok, steel rebars were placed into small cavities and acted as columns.
— Paraphrased from the lecture
| Where in the source | ~21:27–22:41 — anchor: “print like a lost formwork and then” |
| Confidence | high |
Context
In the same summary of the Prvok lessons, Vele (CTU Prague / Scoolpt) describes how Prvok’s walls were made to carry loads and how printing can be used when the weak bond between layers undermines the printed structure itself.
From the transcript
So the way how we dealt with it is that we like created more convex and concave and structured surface and inner parts were like with these small cavities into which we later on put the steel rebars and they worked as a columns. […] So these layer connections are the weakest spots of the whole printing. And somehow it kind of undermines the idea of having a printed object structural[ly] sound. So you can print like a lost formwork and then pour a concrete inside and have like the load bearing parts as the inner parts and not the outer part. In this way you kind of like remove the need to create formwork.
Automatic transcript, presentation, 00:21:27–00:22:09. Lightly cleaned: repeated words and fillers removed, omissions marked […], editorial insertions in [brackets].