Communities argue that electricity going into a data centre is electricity not going into the energy transition or EVs; he accepts this as partly valid and partly not, rather than dismissing it.
— Paraphrased from the lecture
| Where in the source | Q&A ~00:58 — anchor: “one of the most recent points of” |
| Confidence | high |
Context
Answering a student’s question about a data centre that caused a city’s water shortage, Martins (Ramboll) first recalls that for many years the main community objection to data centres was power.
From the transcript
I would say water is one of the most recent points of contention and discussion around data centers, because you know, for many years it was power. […] usually communities will say it’s taking the power away from us, because […] the power that goes into the data center doesn’t go into, you know, the energy transition or electric vehicles or whatever. That is somewhat true, but it is somewhat not true.
Automatic transcript, Q&A, 00:58:00. Lightly cleaned: repeated words and fillers removed, omissions marked […], editorial insertions in [brackets].
Connections
- Source: Cloud in the city – data centres, urban development and implications
- Challenges: Visual impact of logistics on neighbours
- Metrics: Social acceptance
Something wrong or missing? Suggest a correction