Case study · draft

A student project from the Rethinking.Logistics studio showing how tools deliver metrics for decisions.

StudentIlinca Maria Baciu
ProjectLogistics at the Urban Edge
Portfolioheyzine.com/flip-book/443acf12f9.html
StudioAD6 (Kurilla-Prokop studio), Bachelor Diploma Project
Year2026
LocationHostivice industrial zone, western edge of Prague (Czech Republic)
Typologybig-box warehouse park retrofit (existing SEGRO-type logistics zone) with green platforms / canopies
Statusdraft

📖 Open the portfolio

Project

The project looks at the Hostivice industrial zone, an 876,000 m² logistics area that grew next to existing housing over three decades and now separates the town from its landscape through sealed surfaces, truck-dominated roads and monotonous big-box volumes. One representative existing warehouse (about 115 x 110 m, precast concrete frame) is documented in plans, sections and construction details to understand the standard typology. Three urban scenarios (mobility links, a green buffer zone, and zoning that shifts logistics toward the airport) are tested. The design keeps the logistics function but adds a network of raised, tree-like green platforms over and between the warehouses, carrying public routes, green roofs, photovoltaics and rainwater retention, and reconnecting the interrupted green-blue corridor between Prague and Hostivice.

How the student framed the challenge

  • Urban integration of logistics next to housing
  • Sealed surfaces and stormwater runoff on logistics sites
  • Interrupted green-blue ecological corridors
  • Rooftop renewable energy on large warehouses

Metrics and evidence

Every metric the project used, as named by the student, with the value, the calculation and the portfolio page.

MetricStudent’s wordingValueHow it was calculatedToolPage
Rooftop PV generationEnergy productionapprox. 56-88 GWh/year (roof area 350,000-440,000 m²)Assumes 40-50% of the 876,000 m² site is roofed, giving 350,000-440,000 m² of usable roof, multiplied by a typical Central European PV yield per m².manual / formula30
Land takeDeveloped area / building coverageapprox. 350,000-440,000 m² of an 876,000 m² site (about 40-50%)Area of buildings in the industrial zone measured against total site area.not stated29, 30
Parking capacityParking areaapprox. 35,000 m²Measured area of car parking within the zone, used to describe the share of sealed non-building surface.not stated29
—Terrain profileline length 677 m; ascent 38.9 m; altitude 335.5-371.0 m a.s.l.Elevation profile along a section line through the zone, reporting length, total ascent/descent and min/max altitude.not stated (GIS elevation profile, see notes)23
Structural utilisationLoadsroof dead 0.584 / live 0.40 / snow 0.56; office floor dead 10.24 / live 3.00; warehouse floor dead 5.07 / live 5.00 kN/m²Load table for roof, office floor and warehouse ground floor of the case-study building, with material unit weights.manual / formula30
Publicly accessible areaPublicly Accessible Green Space—Listed as a KPI in the questionnaire; no method or value given in the portfolio.not statedquestionnaire only
Mixed-use ratioCommunity Amenity Provision—Listed as the student’s own KPI; no method or value given.not statedquestionnaire only
Green roof coverageGreen Roof—Listed as KPI; portfolio shows green roof and green-roof/PV layers but no quantity.not statedquestionnaire only
Impervious surface ratioPermeable Surface Ratio—Listed as KPI; portfolio describes permeable paving in lighter-traffic areas but no ratio.not statedquestionnaire only
Visual impact on neighboursVisual Impact—Listed as KPI; no method given.not statedquestionnaire only
Energy use intensityEnergy Use Intensity (EUI)—Listed as KPI; not calculated.not statedquestionnaire only
Carbon usage effectivenessCarbon Usage Effectiveness (CUE)—Listed as KPI; not calculated.not statedquestionnaire only
Embodied carbon intensityEmbodied Carbon—Listed as KPI; portfolio discusses concrete-heavy construction and timber/hybrid alternatives qualitatively only.not statedquestionnaire only; qualitative on 31
Operational carbonOperational Carbon—Listed as KPI; not calculated.not statedquestionnaire only

Tools

No digital tool is named in the portfolio — values were estimated by hand, taken from literature, or not quantified.

Trade-offs

  • Adding public and green layers improves urban integration and biodiversity but lowers logistics efficiency and raises construction cost (questionnaire; also listed as unintended consequences).
  • Heavy truck areas must stay hard and durable, limiting the permeable surface ratio; water there is routed to planted channels and retention instead.

Decision

The site analysis and scenarios led to keeping the existing logistics function and adding a connected system of raised green platforms with PV, green roofs, public routes and rainwater retention, rather than replacing the warehouses. The rough PV estimate (56-88 GWh/year) was used to argue that the large roof area is an energy asset.

Open questions

  • No quantified KPI values for green space, permeability, green roof, EUI, CUE or carbon (listed in questionnaire but not calculated in portfolio).
  • CapEx/OpEx, electricity price, grey-water strategy and native species not yet known (questionnaire).
  • No two opposite concept alternatives for the integration vs efficiency trade-off yet.
  • Biggest gaps named: research depth, concept clarity and testing of alternatives (6.2).

Connections